logo  ST. CHARLES PARISH, LA
File #: 2011-0164    Version: 1 Name: Construction Contract with Sealevel Construction, Inc. for Engineer's Canal PS Bar Screen Cleaner Project
Type: Ordinance Status: Enacted
File created: 4/18/2011 In control: Parish Council
On agenda: Final action: 5/2/2011
Enactment date: 5/2/2011 Enactment #: 11-5-3 AMENDED
Title: An ordinance to approve and authorize the execution of a Construction Contract with Sealevel Construction, Inc. for Project No. P090404, Engineer's Canal PS Bar Screen Cleaner Project in the amount of $1,432,981.00.
Sponsors: V.J. St. Pierre Jr., Department of Public Works, Marcus M. Lambert
Indexes: DRO (Engineers Canal Pump Station Bar Screen Cleaners)
Attachments: 1. Section 00500 Agreement signed by Sealevel 2011 04 13.pdf, 2. Engineer's Canal Bid Tabulation by Principal - 2011 04 07.pdf, 3. Engineer's Canal Recommendation of Award from Principal.pdf, 4. 2011-0164 Contract-F, 5. 2011-0164 Final Ord 11-5-3 with Contract, 6. 2011-0164 Completion-F
Related files: 2012-0034, 2012-0150, 2009-0156, 2018-0339, 2019-0184
2011-0164
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
MARCUS M. LAMBERT, COUNCILMAN, DISTRICT VI
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of a Construction Contract with Sealevel Construction, Inc. for Project No. P090404, Engineer's Canal PS Bar Screen Cleaner Project in the amount of $1,432,981.00.
Body
WHEREAS, sealed bids were received by St. Charles Parish on April 7, 2011 for Project No. P090404, Engineer's Canal PS Bar Screen Cleaner Project; and,
WHEREAS, Principal Engineering, Andre Monnot, P.E., the Engineer for the Project, has reviewed the bids and recommend that the Contract be awarded to the low bidder, Sealevel Construction, Inc. in the amount of $1,432,981.00; and,
WHEREAS, the existing Engineer's Canal Pump Station does not have Bar Screen Cleaners installed and the accumulation of debris at the Pump inlets must currently be cleaned manually, automated Bar Screen cleaners will ensure that the pump inlets are maintained in a clean condition, thus enabling the Engineer's Canal Pump Station to operate at maximum efficiency during high rainfall and storm conditions; and,
WHEREAS, the construction costs for this project will be funded with a FEMA Hazard Mitigation Grant (HMGP# 1603c-089-0020, FEMA Project No. 0189) awarded to the Parish in the amount of $1,897,934.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Sealevel Construction, Inc., for the installation of the Bar Screen Cleaners to the Engineer's Canal Pump Station under Project No. P090404, Engineer's Canal PS Bar Screen Cleaner Project, be hereby accepted, in the amount of $1,432,981.00.
SECTION II. That the Parish President is hereby authorized to execute said contract on behalf of the Parish of St. Charles.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows: