Legislation Details

File #: 2026-0325    Version: 1 Name: C.O. No. 2 for the Ormond Center Drainage Improvements (Project No. P190505), to increase the contract amount by $282,632.83 and increase the contract time by fourteen (14) calendar days
Type: Ordinance Status: Introduced For Public Hearing
File created: 9/28/2026 In control: Parish Council
On agenda: 9/28/2026 Final action:
Enactment date: Enactment #:
Title: An ordinance approving and authorizing the execution of Change Order No. 2 for the Ormond Center Drainage Improvements (Project No. P190505), to increase the contract amount by $282,632.83 and increase the contract time by fourteen (14) calendar days.
Sponsors: Matthew Jewell, Department of Engineering, Department of Public Works
Attachments: 1. 2026-0325 Ormond Center Drainage Improvements - Change Order #2 - Partially Executed
Related files: 2023-0319, 2026-0251, 2022-0073, 2025-0191, 2025-0392
2026-0325
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF ENGINEERING)
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ____________
Title
An ordinance approving and authorizing the execution of Change Order No. 2 for the Ormond Center Drainage Improvements (Project No. P190505), to increase the contract amount by $282,632.83 and increase the contract time by fourteen (14) calendar days.
Body
WHEREAS, Ordinance No. 22-4-2 adopted on April 4, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Stuart Consulting Group, Inc., to perform engineering services for Ormond Center Drainage Improvements (Project No. P190505), in the amount not to exceed $81,246.00; and,
WHEREAS, Ordinance No. 23-12-4 adopted on December 4, 2023, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to Ordinance No. 22-4-2 which approved a Professional Services Agreement with Stuart Consulting Group, Inc., for the Ormond Center Drainage Improvements (Project No. P190505), in the not to exceed amount of $171,763.00, increasing the overall contract value to $253,009.00; and,
WHEREAS, Ordinance No. 25-7-13 adopted on July 21, 2025, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 2 to Ordinance 23-12-4, which approved a Professional Services Agreement with Stuart Consulting Group, Inc. for Ormond Center Drainage Improvements (Project No. P190505), in the not to exceed amount of $153,724.20, increasing the overall contract value to $406,733.20; and,
WHEREAS, Ordinance No. 26-1-3 adopted on January 12, 2026, by the St. Charles Parish Council, approved and authorized the execution of a Contract with Cycle Construction Company, LLC, for the Ormond Center Drainage Improvements (Project No. P190505), in the amount of $3,097,730.00; and,
WHEREAS, Ordinance No. 26-8-3 adopted on August 10, 2026, by the St. Charles Parish Council, approve...