An ordinance to approve and authorize the execution of a Construction Contract with Sealevel Construction, Inc. for Project No. P090701, Lakewood Pump Station Bar Screen Cleaner Installation Project in the amount of $1,297,217.00.
Body
WHEREAS, sealed bids were received by St. Charles Parish on June 17, 2010 for Project No. P090701, Lakewood Pump Station Bar Screen Cleaner Installation Project; and,
WHEREAS, Civil & Environmental Consulting Engineer, Danny Hebert, P.E., LLC, the Engineer for the Project, has reviewed the bids and recommend that the Contract be awarded to the low bidder, Sealevel Construction, Inc. in the amount of $1,297,217.00; and,
WHEREAS, the existing Lakewood Pump Station does not have Bar Screen Cleaners installed and the accumulation of debris at the Pump inlets must currently be cleaned manually, automated Bar Screen cleaners will ensure that the pump inlets are maintained in a clean condition, thus enabling the Lakewood Pump Station to operate at maximum efficiency during high rainfall and storm conditions; and,
WHEREAS, the construction costs for this project will be funded with a FEMA Hazard Mitigation Grant awarded to the Parish in the amount of $1,441,000.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Sealevel Construction, Inc., for the installation of bar screen cleaners at the Lakewood Pump Station under Project No. P090701, Lakewood Pump Station Bar Screen Cleaner Installation Project, be hereby approved and accepted, in the amount of $1,297,217.00.
SECTION II. That the Parish President is hereby authorized to execute said contract documents on behalf of St. Charles Parish.