2024-0170
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PARKS AND RECREATION)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the West Bank Bridge Park Improvements, Phase I Lighting, (Project No. RECWBI22), to increase the contract time by 12 days.
Body
WHEREAS, Ordinance No. 22-5-12 adopted on May 16, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Danny J. Hebert, P.E., L.L.C., d.b.a. Civil & Environmental Consulting Engineers to perform engineering services for the Department of Recreation West Bank Bridge Park Improvements, in the amount not to exceed $274,570.00; and,
WHEREAS, Ordinance No. 23-7-15 adopted on July 31, 2023, by the St. Charles Parish Council, approved and authorized the execution of a Contract with All Star Electric, Inc., for the West Bank Bridge Park Improvements, Phase 1 Lighting, (Project No. RECWBI22) in the lump sum amount of $1,189,422.00; and,
WHEREAS, it is necessary to amend the contract resulting in an increase in the contract time by 12 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (Final) for the West Bank Bridge Park Improvements, Phase I Lighting, (Project No. RECWBI22), to increase the contract time by 12 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of ___________, 2024, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED : DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY: ...