File #: 2025-0338    Version: 1 Name: Professional Services Agreement w/ Professional Engineering Consultants Corporation, to perform engineering services for St. Charles Parish West Bank B Plant Clarifier Upgrade (Project No. WWKS 117)
Type: Ordinance Status: Public Hearing
File created: 11/3/2025 In control: Parish Council
On agenda: 11/17/2025 Final action:
Enactment date: Enactment #:
Title: An ordinance approving and authorizing the execution of a Professional Services Agreement with Professional Engineering Consultants Corporation, to perform engineering services for the St. Charles Parish West Bank B Plant Clarifier Upgrade (Project No. WWKS 117), in the amount of $123,256.00.
Sponsors: Matthew Jewell, Department of Waterworks
Attachments: 1. 2025-0338 Professional Engineering Consultants - Professional Services Agreement - October 22, 2025, 2. 2025-0338 Corporate Resolution
2025-0338
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of a Professional Services Agreement with Professional Engineering Consultants Corporation, to perform engineering services for the St. Charles Parish West Bank B Plant Clarifier Upgrade (Project No. WWKS 117), in the amount of $123,256.00.
Body
WHEREAS, St. Charles Parish desires to design the rehabilitation/replacement of thirty- one (31) foot solids contact type clarifier at the West Bank B Water Plant; and,
WHEREAS, the projected work includes but not limited to, removing and replacing the existing solids contact style clarifier. The new clarifier is to have stainless steel on all wetted parts thereby eliminating maintenance (such as blasting and paint) of the unit altogether; and,
WHEREAS, St. Charles Parish wishes to contract with Professional Engineering Consultants Corporation to perform the Plan Development, Bidding and Advertising, and Construction for the St. Charles Parish West Bank B Plant Clarifier Upgrade (Project No. WWKS 117); and,
WHEREAS, St. Charles Parish and Professional Engineering Consultants Corporation have mutually agreed to the amount of $123,256.00 to complete all described in the attached Professional Services Agreement.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Professional Services Agreement between St. Charles Parish and Professional Engineering Consultants Corporation, to perform engineering services for the St. Charles Parish West Bank B Plant Clarifier Upgrade (Project No. WWKS 117), in the amount of $123,256.00 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Agreement on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of...