File #: 2008-0455    Version: 1 Name: Contract with Cajun Constructors, Inc. for project S080501-1 Destrehan WWTP Rehabilitation Phase I Headworks in the amount of $349,500.00
Type: Ordinance Status: Enacted
File created: 11/17/2008 In control: Parish Council
On agenda: Final action: 12/1/2008
Enactment date: 12/1/2008 Enactment #: 08-12-2 AMENDED
Title: An ordinance to approve and authorize the execution of a contract with Cajun Constructors, Inc. for project S080501-1 Destrehan WWTP Rehabilitation Phase I Headworks in the amount of $349,500.00.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: SPW (Destrehan WWTP Rehabilitation Ph. I Headworks)
Attachments: 1. 00500 Cajun Constructors Agreement.pdf, 2. 2008-0455 Contract-F, 3. 2008-0455 Final Ord 08-12-2 with Contract, 4. 2008-0455 Completion-F
Related files: 2012-0076, 2009-0244, 2011-0357, 2012-0185, 2011-0354, 2011-0201, 2009-0100, 2010-0413, 2010-0414, 2009-0306, 2009-0331, 2008-0441
2008-0455
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.                   
Title
An ordinance to approve and authorize the execution of a contract with Cajun Constructors, Inc. for project S080501-1 Destrehan WWTP Rehabilitation Phase I Headworks in the amount of $349,500.00.
Body
WHEREAS,      sealed bids were received by St. Charles Parish on October 30, 2008, for project S080501-1 Destrehan WWTP Rehabilitation Phase I Headworks; and,
WHEREAS,      CH2MHILL, the Engineer for the Project, has reviewed the bids and recommend that the Contract be awarded to the low bidder, Cajun Constructors, Inc., in the amount of $349,500.00; and,
WHEREAS,      the Destrehan Wastewater Treatment Plant services the entire East Bank of St. Charles Parish and repair of the failed lining in the flow divider box is critical to avoiding significant interruption of plant operations.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      That the bid of Cajun Constructors, Inc., for the construction of project S080501-1 Destrehan WWTP Rehabilitation Phase I Headworks, be hereby accepted, in the amount of $349,500.00.
SECTION II.      That the Parish President is hereby authorized to execute the attached contract documents.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this            day of                       , 2008, to become effective five (5) days after publication in the Official Journal.
 
 
 