File #: 2014-0236    Version: 1 Name: Change Order No. 1(Final) for Parish Project No. P990604-3, Coronado Park Area Pump Station #1
Type: Ordinance Status: Enacted
File created: 8/4/2014 In control: Parish Council
On agenda: 8/18/2014 Final action: 8/18/2014
Enactment date: Enactment #: 14-8-12
Title: An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P990604-3, Coronado Park Area Pump Station #1 Drainage Improvements Project to decrease the contract amount by $12,177.00 and increase the contract time by thirty nine (39) days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Coronado Park), Public Works (Dept. of)
Attachments: 1. 2014-0236 Change Order Coronado, 2. 2014-0236 Change Order-F, 3. 2014-0236 Final Ord 14-8-12 with Change Order
Related files: 2009-0079, 2010-0205, 2011-0087, 2011-0179, 2011-0230, 2012-0131, 2012-0217, 2013-0380
2014-0236
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P990604-3, Coronado Park Area Pump Station #1 Drainage Improvements Project to decrease the contract amount by $12,177.00 and increase the contract time by thirty nine (39) days.
body
WHEREAS, Ordinance No. 13-10-18, adopted October 21, 2013, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc. for Parish Project No. P990604-3, Coronado Park Area Pump Station #1 Drainage Improvements Project in the amount of $946,144.00; and,
WHEREAS, The decrease in contract amount resulted from the deletion/decrease of seven line items in the amount of $61,012.00 and an addition/increase of eleven line items in the amount of $48,835.00; and,
WHEREAS, The increase in contract time was a result of an additional twenty one (21) days incurred to fabricate and install the third discharge pipe for the pump station serving the Coronado PS #1; as well as eighteen (18 days) of lost work due to rain events during the duration of the construction of the new Coronado PS #1.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. 1(Final) for Parish Project No. P990604-3, Coronado Park Area Pump Station #1 Drainage Improvements Project to decrease the contract amount by $12,177.00 and increase the contract time by thirty nine (39) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of _________________, 2014,
to become effective five (5) days after publication in the Official Journal.


C...

Click here for full text