logo  ST. CHARLES PARISH, LA
File #: 2001-0219    Version: 1 Name: C. O. No. 1-Final for Dunleith Canal Bank Stabilization, Phase V
Type: Ordinance Status: Enacted
File created: 6/18/2001 In control: Parish Council
On agenda: Final action: 7/2/2001
Enactment date: 7/2/2001 Enactment #: 01-7-2
Title: An ordinance approving and authorizing the execution of Change Order No. 1-Final for Parish Project No. P000309 Dunleith Canal Bank Stabilization, Phase V to decrease the contract amount by $56.88 and to increase the contract time by 41 days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Dunleith Canal Bank Stab., Ph. V)
Attachments: 1. 2001-0219 Change Order-Final, 2. 2001-0219 Final Ord 01-7-2 with Change Order, 3. 2001-0219 Completion-F
Related files: 2000-0505, 2002-0396, 2003-0025, 2003-0199, 2008-0481, 2010-0277, 2011-0021, 2011-0296, 2012-0211, 2012-0418, 2013-0211, 2014-0348, 2014-0402, 2015-0049, 2018-0066, 2017-0216, 2015-0311, 2020-0101, 2016-0299, 2019-0265, 2015-0150, 2015-0241, 2015-0339, 2016-0247, 2019-0347, 2020-0313
2001-0219
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1-Final for Parish Project No. P000309 Dunleith Canal Bank Stabilization, Phase V to decrease the contract amount by $56.88 and to increase the contract time by 41 days.
Body
THE ST. CHARLES PARSIH COUNCIL HEREBY ORDAINS:
SECTION I. Ordinance No. 00-11-1 adopted November 6, 2000 by the St. Charles Parish Council, approved and authorized the execution of a contract with D&O Contractors, Inc. for the construction of Dunleith Canal Bank Stabilization, Phase V in the amount of $182,958.16.
SECTION II. That it is necessary to amend the contract to adjust the original contract quantities with actual quantities and to increase the contract time by 41 calendar days to account for unexpected delays of the Dunleith Canal Bank Stabilization, Phase V.
SECTION III. That it is necessary to decrease the contract amount by $56.88 and increase the contract time by 41 calendar days.
NOW, THEREFORE, BE IT ORDAINED, THAT WE THE MEMBERS OF THE
ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution of Change Order No. 1-Final to the contract for Dunleith Canal Bank Stabilization, Phase V and to decrease the contract amount by $56.88 and increase the contract time by 41 calendar days.
BE IT FURTHER ORDAINED, that the Parish President is hereby authorized to execute this Change Order to the contract.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ___________, 2001,
to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROV...

Click here for full text