File #: 2020-0317    Version: 1 Name: Amend Code, Chapter 25, Article IV, Section 25-52. paragraph (b)(2) to provide downstream overbank flood and property protection for a 25-year, 24-hour storm event
Type: Ordinance Status: Enacted
File created: 11/16/2020 In control: Parish Council
On agenda: 12/7/2020 Final action: 12/7/2020
Enactment date: Enactment #: 20-12-7
Title: An ordinance to amend the St. Charles Parish Code of Ordinances, Chapter 25 - Stormwater Management and Erosion and Sedimentation Control, Article IV, Section 25-52. - Post construction stormwater standards and requirements, paragraph (b)(2) to provide downstream overbank flood and property protection for a 25-year, 24-hour storm event.
Sponsors: Matthew Jewell, Department of Public Works/Wastewater
Indexes: P and Z (Dept. of), Public Works (Dept. of), Subdivision Regulations
Code sections: Ch. 25. - Storm Water Management and Erosion and Sedimentation Control
Attachments: 1. 2020-0317 Recommendation At a Glance (Ch 25 Revision), 2. 2020-0317 Minutes_11.05.2020_Ch 25 rev (2020-9-ORD), 3. 2020-0317 LUR_2020-09_ORD-Overbank Flood Protection, 4. 2020-0317 Final Ord 20-12-7
Related files: 2013-0490, 2013-0491
2020-0317
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS AND WASTEWATER)
ORDINANCE NO. ___________
Title
An ordinance to amend the St. Charles Parish Code of Ordinances, Chapter 25 - Stormwater Management and Erosion and Sedimentation Control, Article IV, Section 25-52. - Post construction stormwater standards and requirements, paragraph (b)(2) to provide downstream overbank flood and property protection for a 25-year, 24-hour storm event.
Body
WHEREAS, Chapter 25 currently requires downstream overbank flood and property protection to be provided by requiring development sites to control the post-development peak discharge rate to the pre-development rate for a 10-year, 24-hour storm event; and,
WHEREAS, the St. Charles Parish Council wishes to increase this to post-development peak discharge rate to the pre-development rate for a 25-year, 24-hour storm event.
NOW, THEREFORE, THE ST PARISH COUNCIL ORDAINS:
SECTION I. That the Code of Ordinances, Chapter 25 - Stormwater Management and Erosion and Sedimentation Control, Article IV, Section 25-52. - Post construction stormwater standards and requirements, paragraph (b)(2), is amended as follows, with additional text in underline and deleted text in strikethrough:
Sec. 25-52. - Post construction stormwater standards and requirements.
(b) Post-development stormwater management performance criteria.
(2) Overbank flooding protection of bayous and waterways. Downstream overbank flood and property protection shall be provided by controlling the post-development peak discharge rate to the pre-development rate for the ten25-year, twenty-four24-hour return frequency storm event.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _______ day of __________, 2020 to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESI...