File #: 2025-0026    Version: 1 Name: C.O. No. 3 (Final) for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to decrease the contract amount by $64,132.57
Type: Ordinance Status: Enacted
File created: 2/10/2025 In control: Parish Council
On agenda: 2/24/2025 Final action: 2/24/2025
Enactment date: Enactment #: 25-2-9
Title: An ordinance approving and authorizing the execution of Change Order No. 3 (Final) for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to decrease the contract amount by $64,132.57.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Canal Imp. Near Destrehan Pump Station No. 2), Public Works (Dept. of)
Attachments: 1. 2025-0026 P181101 Change Order #3 - Partially Executed, 2. 2025-0026 Final Ord 25-2-9 with change order, 3. 2025-0026 Recordation Documents, 4. 2025-0026 Correspondence 02.27.2025
Related files: 2024-0119, 2020-0200, 2019-0193, 2023-0157, 2023-0141, 2024-0320, 2023-0143
2025-0026
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of Change Order No. 3 (Final) for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to decrease the contract amount by $64,132.57.
Body
WHEREAS, Ordinance No. 19-7-3 adopted July 1, 2019, by the St. Charles Parish Council, approved and authorized the execution professional service multi-phase project agreement with Picciola & Associates, Inc., for providing all necessary professional engineering services for a project that increases the trash screen capacity and the size of the sump into Destrehan Pump Station (P.S.) No. 2. (Parish Project Number P181101); and,
WHEREAS, Ordinance No. 20-7-13 adopted July 27, 2020, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to the professional services agreement with Picciola & Associates, Inc., for providing necessary professional engineering services for a project that improves the hydraulic capacity into Destrehan Pump Station (P.S.) No. 2 (Parish Project Number P181101), in the amount not to exceed $54,927.00, increasing the overall not to exceed contract amount to $238,302.00; and,
WHEREAS, Ordinance No. 23-6-10 adopted June 19, 2023, by the St. Charles Parish Council, approved and authorized the execution of a Contract with Sealevel Construction, Inc., for Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the amount of $9,190,697.00; and,
WHEREAS, Ordinance No. 23-6-12 adopted June 19, 2023, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Alpha Testing and Inspection, Inc., to perform testing services for Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the not to exceed amount of $66,000.00; and,
WHEREAS, Ordinance No...