2015-0267
INTRODUCED BY: V.J. St. Pierre, jr., PARISH PRESIDENT
(DEPARTMENT OF PLANNING AND ZONING/CZM)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Bertucci Contracting Company, LLC, for PO-43 East LaBranche Shoreline Protection Project, Coastal Impact Assistance Program to decrease the contract time by 212 days.
Body
WHEREAS, Ordinance No. 15-3-2 adopted April 6, 2015 by the St. Charles Parish Council awarded construction of the East LaBranche Shoreline Protection Project to Bertucci Contracting Company, LLC; and,
WHEREAS, the St. Charles Parish Council approved Change Order No. 1 for PO-43 East LaBranche Shoreline Protection Project, Coastal Impact Assistance Program to increase the contract amount by $254,415.96 in Ordinance No. 15-6-20 on June 15, 2015; and,
WHEREAS, it is necessary to amend the contract to reduce the days of the contract by 212 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 2 (Final) for Bertucci Contracting Company, LLC, for PO-43 East LaBranche Shoreline Protection Project, Coastal Impact Assistance Program to decrease the contract time by 212 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
SECTION III. St. Charles Parish considers the project complete and accepts all improvements and modifications installed during execution of the project.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2015, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: