File #: 2025-0259    Version: 1 Name: Professional Service Agreement with Waggoner Engineering, Inc. to perform engineering services for the East Bank A and B Plant Demolition (Project No. WWKS 116)
Type: Ordinance Status: Enacted
File created: 9/8/2025 In control: Parish Council
On agenda: 9/22/2025 Final action: 9/22/2025
Enactment date: Enactment #: 25-9-2
Title: An ordinance approving and authorizing the execution of a Professional Service Agreement with Waggoner Engineering, Inc. to perform engineering services for the East Bank A and B Plant Demolition (Project No. WWKS 116), in the lump sum amount of $213,023.00.
Sponsors: Matthew Jewell, Department of Waterworks
Attachments: 1. 2025-0259 Waggoner Engineering - Professional Services Agreement - August 12, 2025 (1), 2. 2025-0259 Waggoner Engineering - Corporate Resolution - August 12, 2025, 3. 2025-0259 Correspondence 09.29.2025, 4. 2025-0259 Final Ord. 25-9-2 with Agreement, 5. 2025-0259 Correspondence 10.1.2025
2025-0259
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of a Professional Service Agreement with Waggoner Engineering, Inc. to perform engineering services for the East Bank A and B Plant Demolition (Project No. WWKS 116), in the lump sum amount of $213,023.00.
Body
WHEREAS, St. Charles Parish desires to demolish infrastructure associated with East Bank A & B plants; and,
WHEREAS, the projected work includes, but not limited to: demolish, excavate, haul and dispose of an existing 50-ft diameter x 10-ft deep concrete storage tank; demolish, excavate, haul and dispose of the existing approx. 6,000 SF (footprint) structures of treatment trains A & B; demolish, excavate, haul and dispose of the existing concrete tank and treatment trains A & B concrete foundations, including plotting existing piles; Abandon in place and reroute subsurface pipelines at various locations as a result of the proposed demolition work and backfill, grade and hydroseed all excavated/disturbed areas; and,
WHEREAS, St. Charles Parish wishes to contract with Waggoner Engineering, Inc., to perform the Plan Development, Bidding and Advertising, and Construction for the East Bank A and B Plant Demolition (Project No. WWKS 116), as described in Attachments A, B, and C.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Professional Services Agreement between St. Charles Parish and Waggoner Engineering, Inc. the East Bank A and B Plant Demolition (Project No. WWKS 116), in the lump sum amount of $213,023.00 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Agreement on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows: