logo  ST. CHARLES PARISH, LA
File #: 2021-0117    Version: 1 Name: Amendment No. 1 to Ord. No. 18-6-5 w/GSA Consulting Engineers for necessary professional engineering services associated with Parish Project No. WWKS 96, East Bank C Plant Filter Upgrade
Type: Ordinance Status: Enacted
File created: 4/19/2021 In control: Parish Council
On agenda: 5/3/2021 Final action: 5/3/2021
Enactment date: Enactment #: 21-5-5
Title: An ordinance to approve and authorize the execution of Amendment No. 1 to Ordinance No. 18-6-5 which approved a contract for Engineering Services with GSA Consulting Engineers for necessary professional engineering services associated with Parish Project No. WWKS 96, East Bank C Plant Filter Upgrade.
Sponsors: Matthew Jewell, Department of Waterworks
Indexes: WW (EB C Plant Filter Upgrade)
Attachments: 1. 2021-0117 EAST BANK C PLANT UPGRADE (WWKS 96) Amendment No. 1_REV.pdf, 2. 2018-0147 Final Ord 18-6-5 with Contract.pdf, 3. 2021-0117 Final Ord 21-5-5 with amendment
Related files: 2018-0147, 2021-0198, 2023-0052, 2024-0229
2021-0117
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of Amendment No. 1 to Ordinance No. 18-6-5 which approved a contract for Engineering Services with GSA Consulting Engineers for necessary professional engineering services associated with Parish Project No. WWKS 96, East Bank C Plant Filter Upgrade.
Body
WHEREAS, on June 4, 2018, the St. Charles Parish Council approved Ordinance No. 18-6-5 authorizing the execution of a Contract for Engineering Services with GSA Consulting Engineers for Parish Project No. WWKS 96, East Bank C Plant Filter Upgrade; and,
WHEREAS, it is necessary to amend the contract and modify the scope of work, Section 2.0 Character and Extent of Basic Services of the Engineer, Section 2.1.2.; and Compensation Section 4.0, by adding section 4.2.4.1; and,
WHEREAS, for the additional engineering associated with Amendment No. 1, the Owner shall authorize and pay the Engineer a lump sum fee not to exceed a total $21,100.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Amendment No. 1 to Ordinance No. 18-6-5, a contract for Engineering Services between GSA Consulting Engineers and the Parish of St. Charles for necessary professional engineering services associated with Parish Project No. WWKS 96, East Bank C Plant Filter Upgrade, amending Section 2.0 Character and Extent of Basic Services of the Engineer, Section 2.1.2 and Section 4.0 Compensation, by adding Section 4.2.4.1 to the contract, is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Amendment No. 1 on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ____________, 2021 to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:______________...

Click here for full text