logo  ST. CHARLES PARISH, LA
File #: 2009-0071    Version: 1 Name: C. O. No. 1 Road Maintenance 2008, to add a line item for 10-Inch Depth Portland Cement Concrete Pavement and to increase the contract amount by $85,421.80
Type: Ordinance Status: Enacted
File created: 3/2/2009 In control: Parish Council
On agenda: Final action: 3/16/2009
Enactment date: 3/16/2009 Enactment #: 09-3-11
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P060405, Road Maintenance 2008, to add a line item for 10-Inch Depth Portland Cement Concrete Pavement and to increase the contract amount by $85,421.80.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Road Overlay 2008)
Attachments: 1. 2009-0071 Change Order-F, 2. 2009-0071 Final Ord 09-3-11 with Change Order
Related files: 2006-0145, 2008-0501, 2009-0202
2009-0071
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P060405, Road Maintenance 2008, to add a line item for 10-Inch Depth Portland Cement Concrete Pavement and to increase the contract amount by $85,421.80.
Body
WHEREAS, Ordinance No. 09-1-7 adopted January 5, 2009 by the St. Charles Parish Council awarded construction of Parish Project No. P060405, Road Maintenance 2008, to Byron E. Talbot Contractors; and,
WHEREAS, during an investigation of a water leak on James Drive East, it was discovered that the road was ten inches (10”) thick instead of eight inches (8”) thick as was listed in the Contract; and,
WHEREAS, it is in the best interest of St Charles Parish to replace sections of James Drive East, as stated in the Contract, with a ten inch (10”) thick road; and,
WHEREAS, it is necessary to amend the contract to and a line item for the installation of ten inch (10”) thick road and to also adjust the original contract quantities with current quantities resulting in an increase to the contract amount by $85,421.80.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. 1 for Parish Project No. P060405, Road Maintenance 2008, to add a line item for 10-Inch Depth Portland Cement Concrete Pavement and to increase the contract amount by $85,421.80.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of _______, 2009, to become effective five (5) days after this publication in the official journal.