2024-0037
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of a Change Order No. 1 and Final for the Hurricane Ida Repairs and Reconstruction, Department of Waterworks, West Bank Facilities (Project Numbers WWKS 107 and WWKS 108-334) to increase the contract amount by $4,727.00 and to increase the contract time by 5 calendar days.
Body
WHEREAS, Ordinance No. 23-3-8 adopted March 27, 2023, by the St. Charles Parish Council, approved and authorized the execution of a Contract with Pintail Contracting Services, LLC, for Hurricane Ida Repairs and Reconstruction, Department of Waterworks, West Bank Facilities (Project Numbers WWKS 107 & WWKS 108-334) in the amount of $1,432,000.00; and,
WHEREAS, it is necessary to amend the construction contract to delete the work item Project Identification Sign, resulting in a decrease to the contract amount by $3,000.00; and,
WHEREAS, it is necessary to amend the construction contract to delete the work item Building Plaque, resulting in a decrease in the contract amount of $2,800.00; and,
WHEREAS, it is necessary to amend the construction contract to delete the work item Mag Lock Card Reader, resulting in a decrease in the contract of $12,500.00; and,
WHEREAS, it is necessary to amend the construction contract to add the work item Asbestos Removal, and increase the contract amount $13,129.00; and,
WHEREAS, it is necessary to amend the construction contract to add the work item A Wood Framing, and increase the contract amount $5,561.00; and,
WHEREAS, it is necessary to amend the construction contract to add the work item Demolition and Replacement of sidewalk, and increase the contract amount $4,337.00; and,
WHEREAS, the increase of contract time by five (5) calendar days is to account for labor associated with the additional work items; and,
WHEREAS, the amending items now reflect the final contract price as $1,436,7...