Title: An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P081102-2 Dunleith Canal Stabilization - Phase I to decrease the contract amount by $19,491.01 and decrease the contract time by five (5) days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Dunleith Canal Stab., Ph. 1)
Attachments: 1. 2011-0021 Change Order-F, 2. 2011-0021 Final Ord 11-1-7 with Change Order
Related files: 2000-0505, 2001-0219, 2002-0396, 2003-0025, 2003-0199, 2008-0481, 2010-0277, 2011-0296, 2012-0211, 2012-0418, 2013-0211, 2014-0348, 2014-0402, 2015-0049, 2015-0339, 2018-0066, 2020-0101, 2015-0150, 2015-0241, 2015-0311, 2016-0247, 2016-0299, 2017-0216, 2019-0265, 2019-0347, 2020-0313
2011-0021
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P081102-2 Dunleith Canal Stabilization - Phase I to decrease the contract amount by $19,491.01 and decrease the contract time by five (5) days.
Body
WHEREAS, Ordinance No. 10-8-13, adopted August 23, 2010, by the St. Charles Parish Council, approved and authorized the execution of a contract with Advance Quality Construction, Inc. for Parish Project No. P081102-2 Dunleith Canal Stabilization - Phase I in the amount of $614,282.00; and,
WHEREAS, the decrease in contract amount resulted from the deletion of two line items in the amount of $40,290.00, decreasing two lines item in the amount of $3,943.01, and increasing two line items in the amount of $24,742.00; and,
WHEREAS, the decrease in contract time was a result of excellent weather and contractor management of their schedule.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1(Final) for Parish Project No. P081102-2 Dunleith Canal Stabilization - Phase I to decrease the contract amount by $19,491.01 and decrease the contract time by five (5) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ____________, 2011, to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________

PARISH PRESIDENT:_____________________________________...