logo  ST. CHARLES PARISH, LA
File #: 2012-0200    Version: 1 Name: Change Order No. 1 (Final) for Eighty Arpent Pump Station Improvements Project
Type: Ordinance Status: Enacted
File created: 5/21/2012 In control: Parish Council
On agenda: Final action: 6/4/2012
Enactment date: 6/4/2012 Enactment #: 12-6-8
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Project No. P080801, Eighty Arpent Pump Station Improvements Project to decrease the contract amount by $175,126.50 and increase the contract time by seventy eight (78) days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Eighty Arpent Pump Station Upgrade)
Attachments: 1. Change Order for 80 Arpent.pdf, 2. 2012-0200 Change Order-F, 3. 2012-0200 Final Ord 12-6-8 with Change Order
Related files: 2009-0061, 2011-0022
2012-0200
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Project No. P080801, Eighty Arpent Pump Station Improvements Project to decrease the contract amount by $175,126.50 and increase the contract time by seventy eight (78) days.
Body
WHEREAS, Ordinance No. 11-1-8, adopted January 24, 2011, by the St. Charles Parish Council, approved and authorized the execution of a contract with BLD Services LLC for Project No. P080801, Eighty Arpent Pump Station Improvements Project in the amount of $6,965,925.00; and,
WHEREAS, The decrease in contract amount resulted from the net decrease of twenty (20) bid line items in the amount of $325,159.50, and an increase of fourteen (14) additional line items in the amount of $150,033.00; and,
WHEREAS, The increase in contract time was a result of additional days incurred due to rain events throughout the duration of the project and late delivery of new Pumps, Gear Boxes and Engines due to manufacturer delays.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. 1(Final) for Parish Project No. P080801, Eighty Arpent Pump Station Improvements Project to decrease the contract amount by $175,126.50 and increase the contract time by seventy eight (78) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
SECTION III. St Charles Parish considers the project complete and accepts all equipment installations, repairs, and modifications installed during execution of the project.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ___________, 2012,
to become effective five (5) days after publication in the Official Journal.


...

Click here for full text