File #: 2024-0048    Version: 1 Name: C.O. No. 1 for the Hydraulic Bottleneck Near Destrehan P.S. No. 2, (Project No. P190507), to increase the contract amount by $476,447.31 and increase the contract time by 76 days
Type: Ordinance Status: Enacted
File created: 1/22/2024 In control: Parish Council
On agenda: 2/5/2024 Final action: 2/5/2024
Enactment date: Enactment #: 24-2-6
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for the Hydraulic Bottleneck Near Destrehan P.S. No. 2, (Project No. P190507), to increase the contract amount by $476,447.31 and increase the contract time by 76 days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Canal Imp. Near Destrehan Pump Station No. 2)
Attachments: 1. 2024-0048 P190507 Signed Copy of Change Order #1, 2. 2024-0048 P190507 - Change Order #1 Supporting Documents, 3. 2024-0048 Final Ord 24-2-6 with change order, 4. 2024-0048 Recordation Documents
Related files: 2023-0310, 2019-0183, 2022-0338, 2023-0099, 2024-0202, 2024-0069
2024-0048
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for the Hydraulic Bottleneck Near Destrehan P.S. No. 2, (Project No. P190507), to increase the contract amount by $476,447.31 and increase the contract time by 76 days.
Body
WHEREAS, Ordinance No. 19-7-1 adopted July 1, 2019, by the St. Charles Parish Council, approved and authorized the execution of a professional service multi-phase project agreement with Evans-Graves Engineers, Inc., for providing all necessary professional engineering services for a project that improves conveyance capacity in a canal in the vicinity of Destrehan Pump Station (P.S.) No. 2. (Parish Project Number P190507), in the amount not to exceed $105,160.00; and,
WHEREAS, Ordinance No. 22-12-7 adopted December 5, 2022, by the St. Charles Parish Council, approved and authorized the execution of a contract with Cycle Construction Company, LLC, for the Hydraulic Bottleneck Near Destrehan P.S. No. 2, (Project No. P190507) in the amount of $2,264,960.00; and,
WHEREAS, Ordinance No. 23-5-2 adopted May 8, 2023, by the St. Charles Parish Council, approved and authorized the executions of a Professional Services Agreement with Alpha Testing and Inspection, Inc., to perform testing services for the Hydraulic Bottleneck Near Destrehan P.S. No. 2 (Project No. P190507), in the not to exceed amount of $26,000.00; and,
WHEREAS, Ordinance No. 23-11-12 adopted November 20, 2023, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to a Professional Services Agreement with Alpha Testing and Inspection, Inc., for additional testing services for the Hydraulic Bottleneck Near Destrehan P.S. No. 2 (Project No. P190507), in the not to exceed amount of $19,000.00, increasing the overall not to exceed fee to $45,000.00; and,
WHEREAS, it is necessary to amend the construction contr...

Click here for full text