logo  ST. CHARLES PARISH, LA
File #: 2001-0060    Version: 1 Name: Revoke the Program Management Services with Hartman Engineering, Inc. for the Wastewater Regionalization Program
Type: Ordinance Status: Failed
File created: 2/19/2001 In control: Parish Council
On agenda: Final action: 3/19/2001
Enactment date: Enactment #:
Title: An ordinance to revoke the Program Management Services with Hartman Engineering, Inc. for the Wastewater Regionalization Program.
Sponsors: 'Ram' Ramchandran, Terry Authement, Barry Minnich
Indexes: SPW (Program Management Services for Wastewater Regionalization Program)
Attachments: 1. 2001-0060 Failed Proposed Ordinance
Related files: 2000-0160, 2000-0310, 2000-0517
2001-0060
INTRODUCED BY: 'RAM' RAMCHANDRAN, COUNCILMAN AT LARGE, DIVISION A
TERRY AUTHEMENT, COUNCILMAN, DISTRICT IV
BARRY MINNICH, COUNCILMAN, DISTRICT VII
ORDINANCE NO.
Title
An ordinance to revoke the Program Management Services with Hartman Engineering, Inc. for the Wastewater Regionalization Program.
Body
WHEREAS, on November 20, 2000, the Parish Council adopted Ordinance No. 00-11-11 approving a Contract for Engineering Services with Hartman Engineering, Inc. for Program Management for Capital Outlay, Environmental Management, and Wastewater System Improvements and Evaluations Projects; and,
WHEREAS, on July 10, 2000, the Parish Council adopted Ordinance No. 00-7-7 approving a Contract for Engineering Services with Hartman Engineering, Inc. for Program Management Services for the Wastewater Regionalization Program; and,
WHEREAS, on April 3, 2000, the Parish Council adopted Ordinance No. 00-4-13 approving a Contract with Hartman Engineering, Inc. for Program Management Services for the Wastewater Regionalization Program; and,
WHEREAS, the Regional Wastewater Plant Project has reached close to a maximum of $41 Million Dollars as approved by the voters of this Parish; and,
WHEREAS, during the January 29, 2000, Operations, Maintenance, and Construction Management Committee Meeting, the Public Works Director reported that 99% of this Project is complete as originally envisioned and approved by the Council. Further contingencies of this Project is not evaluated by the Qualification Based Selection Review Panel; and,
WHEREAS, the Council desires to separate new Capital Projects from approved Capital Projects within the Wastewater Department.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. Due to the completion of originally assigned Program Management tasks we hereby revoke the Program Management Contracts with Hartman Engineering, Inc. as the Council promised the voters of this Parish to stay under the capi...

Click here for full text