logo  ST. CHARLES PARISH, LA
File #: 2023-0341    Version: 1 Name: C.O. No. 1 (Final) for the St. Charles Memorial Plaza (Project No. CMPK0418)
Type: Ordinance Status: Enacted
File created: 12/4/2023 In control: Parish Council
On agenda: 12/18/2023 Final action: 12/18/2023
Enactment date: Enactment #: 23-12-9
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles Parish Memorial Plaza (Parish Project No. CMPK0418), to decrease the contract amount by $2,158.05 and increase the contract time by 409 days.
Sponsors: Matthew Jewell, Department of Parks and Recreation
Indexes: Government Bldgs., P and R (Dept. of) (Memorial Park)
Attachments: 1. 2023-0341 Memorial Plaza Change Order, 2. 2023-0341 Final Ord 23-12-9 with change order, 3. 2023-0341 Recordation Documents
Related files: 2020-0123, 2021-0193
2023-0341
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PARKS AND RECREATION)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles Parish Memorial Plaza (Parish Project No. CMPK0418), to decrease the contract amount by $2,158.05 and increase the contract time by 409 days.
Body
WHEREAS, Ordinance No. 20-5-12 adopted on May 18, 2020, by the St. Charles Parish Council, approved and authorized the execution of a Engineering Services Contract with Linfield, Hunter & Junius, Inc. for the design and construction management of a Memorial Park to be located at 274 Judge Edward Dufresne Parkway, Luling, LA.; and,
WHEREAS, Ordinance No. 21-8-4 adopted on August 9, 2021, by the St. Charles Parish Council, approved and authorized the execution of a Contract with LA Contracting Enterprises, LLC, for the St. Charles Parish Memorial Plaza Project (Parish Project No. CMPK0418) located at the Edward A. Dufresne Community Center, 274 Judge Edward Dufresne, Luling, LA, in the amount of $1,399,825.00; and,
WHEREAS, It is necessary to issue a change order to add 409 days to the contract due to a delay in shipping which was Covid related; and,
WHEREAS, It is necessary to amend the contract resulting in an increase in the approved contract time from 120 calendar days to 529 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (Final) for the St. Charles Parish Memorial Plaza (Parish Project No. CMPK0418), to decrease the contract amount by $2,158.05 and increase the contract time by 409 days and is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ___________, 2023, to be...