File #: 2025-0033    Version: 1 Name: Professional Services Agreement with Barowka and Bonura Engineers and Consultants, LLC to perform engineering services for the Cousins Canal Bank Stabilization (Project No. P241103), in the not to exceed amount of $618,000.00.
Type: Ordinance Status: Enacted
File created: 2/10/2025 In control: Parish Council
On agenda: 2/24/2025 Final action: 2/24/2025
Enactment date: Enactment #: 25-2-16
Title: An ordinance approving and authorizing the execution of a Professional Services Agreement with Barowka and Bonura Engineers and Consultants, LLC, to perform engineering services for the Cousins Canal Bank Stabilization (Project No. P241103), in the not to exceed amount of $618,000.00.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Cousins Canal Bank Stab.), Public Works (Dept. of)
Attachments: 1. 2025-0033 Barowka and Bonura Engineers and Consul...- Cousins Canal Bank Stabilization, 2. 2025-0033 Barowka and Bonura Engineers and Consul...LC - Rate Sheet - January 09, 2025, 3. 2025-0033 Barowka and Bonura Engineers and Consul...rate Resolution - January 09, 2025, 4. 2025-0033 Amended Barowka and Bonura Engineers and Consultants, LLC - Professional Services Agreement - Cousins Canal Bank Stabilization, 5. 2025-0033 Final Ord 25-2-16 with agreement, 6. 2025-0033 Correspondence 02.26.2025, 7. 2025-0033 Correspondence 03.13.2025

2025-0033

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

                                                               (DEPARTMENT OF Public Works)

ORDINANCE NO.  ___________

Title

An ordinance approving and authorizing the execution of a Professional Services Agreement with Barowka and Bonura Engineers and Consultants, LLC, to perform engineering services for the Cousins Canal Bank Stabilization (Project No. P241103), in the not to exceed amount of $618,000.00.

Body

WHEREAS,                     St. Charles Parish desires to have the banks of Cousins Canal stabilized with sheet piling; and,

WHEREAS,                     St. Charles Parish and Barowka and Bonura Engineers and Consultants, LLC, have mutually agreed to perform engineering services for the Cousins Canal Bank Stabilization (Project No. P241103), in the not to exceed amount of $618,000.00; and,

WHEREAS,                     the Professional Services Agreement between St. Charles Parish and Barowka and Bonura Engineers and Consultants, LLC, describes the details of the proposed services and compensation.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That the Professional Services Agreement between St. Charles Parish and Barowka and Bonura Engineers and Consultants, LLC, to perform engineering services for the Cousins Canal Bank Stabilization (Project No. P241103), in the not to exceed amount of $618,000.00, is hereby approved and accepted

SECTION II.                     That the Parish President is hereby authorized to execute said Agreement on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this ______ day of __________, 2025, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED :                       DISAPPROVED:                                           

 