logo  ST. CHARLES PARISH, LA
File #: 2024-0137    Version: 1 Name: C.O. No. 2 (Final) for Ellington Structures - Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project
Type: Ordinance Status: Enacted
File created: 4/15/2024 In control: Parish Council
On agenda: 5/6/2024 Final action: 5/6/2024
Enactment date: Enactment #: 24-5-2
Title: An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for the Ellington Structures - Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project, to decrease the contract amount by $76,103.06 and decrease the contract time by forty-one (41) days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: CZM, Grants, Hurricane Protection Levee (WB - Ellington), Hurricane Protection Levee (WB - Kellogg Pump Station T-Wall)
Attachments: 1. 2024-0137 Kellogg T-Wall Final Change Order, 2. 2024-0137 Letter, 3. 2024-0137 Final Ord 24-5-2 with change order, 4. 2024-0137 Recordation Documents
Related files: 2008-0418, 2022-0356, 2022-0063, 2020-0324
2024-0137
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for the Ellington Structures - Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project, to decrease the contract amount by $76,103.06 and decrease the contract time by forty-one (41) days.
Body
WHEREAS, Ordinance No. 08-10-7 adopted October 20, 2008, by the St. Charles Parish Council, approved and authorized the execution of a Contract for Engineering Services with BURK-KLEINPETER, INC. for necessary professional engineering services associated with Parish Project No. P080905 St. Charles Parish West Bank Hurricane Protection Levee and Urban Flood Control; and,
WHEREAS, Resolution No. 6522 adopted on November 16, 2020, by the St. Charles Parish Council, approved and authorized the execution of an Intergovernmental Agreement between the State of Louisiana through the Coastal Protection and Restoration Authority Board and St. Charles Parish Government regarding the construction of the Kellogg Pump Station T-Wall (BA-0244) project in Luling to provide $2,500,000.00 in funding for the construction costs of said project; and,
WHEREAS, Ordinance 22-3-12 adopted March 21, 2022, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc., for Project No. P080905-5F, CPRA Project No. BA-0244, Ellington Structures-Kellogg Pump Station T-Wall, as part of the West Bank Hurricane Protection Levee Project, in the amount of $4,323,888.00; and,
WHEREAS, Ordinance 23-1-5 adopted January 23, 2023, by the St. Charles Parish Council, approved and authorized Change Order No. 1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Le...

Click here for full text