An ordinance to amend Ordinance No. 09-12-12 an Engineering Services contract with Jordan Jones & Goulding for the East Bank C Plant Clarifier Refurbishment to reassign all responsibilities under said contract to JACOBS Engineering.
Body
WHEREAS, the St. Charles Parish Council adopted Ordinance No. 09-12-12 on December 21, 2009 approving a contract for engineering services for the East Bank C Plant Clarifier Refurbishment with Jordan Jones & Goulding; and,
WHEREAS, Since that time Jordan Jones & Goulding has been wholly acquired by JACOBS Engineering; and,
WHEREAS, St. Charles Parish desires to continue its working relationship with the engineering firm as it relates to the East Bank C Plant Clarifier Refurbishment project.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Amendment No. 1 to Ordinance No. 09-12-12 is hereby approved to reassign all responsibilities under said contract from Jordan Jones & Goulding to JACOBS Engineering for the East Bank C Plant Clarifier Refurbishment.
SECTION II. That the Parish President is hereby authorized to execute said Amendment No. 1 on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of 2010, to become effective five (5) days after publication in the Official Journal.