logo  ST. CHARLES PARISH, LA
File #: 2010-0371    Version: 1 Name: Amend Ordinance No. 09-12-12 an Engineering Services contract with Jordan Jones & Goulding for the East Bank C Plant Clarifier Refurbishment to reassign all responsibilities under said contract to JACOBS Engineering
Type: Ordinance Status: Enacted
File created: 10/18/2010 In control: Parish Council
On agenda: Final action: 11/8/2010
Enactment date: 11/8/2010 Enactment #: 10-11-6
Title: An ordinance to amend Ordinance No. 09-12-12 an Engineering Services contract with Jordan Jones & Goulding for the East Bank C Plant Clarifier Refurbishment to reassign all responsibilities under said contract to JACOBS Engineering.
Sponsors: V.J. St. Pierre Jr., Department of Waterworks
Indexes: WW (EB Clarifier, Planning and Construction)
Attachments: 1. Ordinance - Amend to ENG - Amend No 1.doc, 2. 2010-0371 Contract-F, 3. 2010-0371 Final Ord 10-11-6 with Amendment
Related files: 2012-0214, 2009-0472, 2013-0175
2010-0371
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO.  ___________
Title
An ordinance to amend Ordinance No. 09-12-12 an Engineering Services contract with Jordan Jones & Goulding for the East Bank C Plant Clarifier Refurbishment to reassign all responsibilities under said contract to JACOBS Engineering.
Body
WHEREAS,      the St. Charles Parish Council adopted Ordinance No. 09-12-12 on December 21, 2009 approving a contract for engineering services for the East Bank C Plant Clarifier Refurbishment with Jordan Jones & Goulding; and,
WHEREAS,      Since that time Jordan Jones & Goulding has been wholly acquired by JACOBS Engineering; and,
WHEREAS,      St. Charles Parish desires to continue its working relationship with the engineering firm as it relates to the East Bank C Plant Clarifier Refurbishment project.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.      That Amendment No. 1 to Ordinance No. 09-12-12 is hereby approved to reassign all responsibilities under said contract from Jordan Jones & Goulding to JACOBS Engineering for the East Bank C Plant Clarifier Refurbishment.
      SECTION II.      That the Parish President is hereby authorized to execute said Amendment No. 1 on behalf of St. Charles Parish.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this       ______ day of                    2010, to become effective five (5) days after publication in the Official Journal.
 
 
 
 
CHAIRMAN:                                          
SECRETARY:                                          
DLVD/PARISH PRESIDENT:                              
APPROVED:                  DISAPPROVED:                  
 
PARISH PRESIDENT:                                    
RETD/SECRETARY:                                    
AT:                        RECD BY: