File #: 2017-0239    Version: 1 Name: Change Order No. 1 (Final) for the construction of Federal Project No. 22-00929, Rathborne Park Development, Phase II
Type: Ordinance Status: Enacted
File created: 7/31/2017 In control: Parish Council
On agenda: 8/14/2017 Final action: 8/14/2017
Enactment date: Enactment #: 17-8-2
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the construction of Federal Project No. 22-00929, Rathborne Park Development, Phase II, to decrease the contract amount by $2,078.04 and increase the contract time 40 days.
Sponsors: Lawrence 'Larry' Cochran, Department of Parks and Recreation
Indexes: Lakewood - Lakewood Ridge Subd., Luling, P and R (Dept. of) (Rathborne Park Dev., Ph. II)
Attachments: 1. 2017-0239 C.O. Rathborne Park, Ph. II, 2. 2017-0239 Change Order-F, 3. 2017-0239 Final Ord 17-8-2 with Change Order
Related files: 2010-0118, 2010-0114, 2008-0320, 2009-0101, 2010-0104, 2010-0112, 2008-0163, 2012-0120, 2012-0377, 2010-0349, 2010-0383, 2011-0209, 2014-0155, 2016-0407, 2013-0458, 2013-0130, 2013-0179, 2018-0115, 2020-0144, 2015-0149, 2018-0123, 2019-0363

2017-0239

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF PARKS & RECREATION)

ORDINANCE NO. _________

Title

An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the construction of Federal Project No. 22-00929, Rathborne Park Development, Phase II, to decrease the contract amount by $2,078.04 and increase the contract time 40 days.

Body

WHEREAS,                     Ordinance No. 16-12-5 adopted December 12, 2016, by the St. Charles Parish Council awarded construction of Federal Project No. 22-00929, Rathborne Park Development, Phase II; and,

WHEREAS,                     it is necessary to adjust the original contract to reflect those items more fully described in Change Order No. 1 and decrease the dollar amount by $2,078.04 and increase the contract time 40 days as a result of additional requested work.  Final Contract Price will be $644,992.91.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That Change Order Change Order No. 1 (Final) for the construction of Federal Project No. 22-00929, Rathborne Park Development, Phase II, to decrease the contract amount by $2,078.04 and increase the contract time 40 days is hereby approved and accepted.

                     SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ______ day of __________, 2017, to become effective five (5) days after this publication in the official journal.

2017-0239 C.O. No. 1 Rathborne Park, Phase II

 

 

CHAIRMAN:                                                                                                                                                   

SECRETARY:                                                                                                                                                   

DLVD/PARISH PRESIDENT:                                                                                                         

APPROVED:                                                               DISAPPROVED:                                                               

 

PARISH PRESIDENT:                                                                                                                              

RETD/SECRETARY:                                                                                                                              

AT:                                                                                    RECD BY: