logo  ST. CHARLES PARISH, LA
File #: 2005-0063    Version: 1 Name: Change Order No. Two (2) - Final for East Bank Historical Lighting
Type: Ordinance Status: Enacted
File created: 2/21/2005 In control: Parish Council
On agenda: Final action: 3/21/2005
Enactment date: 3/21/2005 Enactment #: 05-3-7
Title: An ordinance approving and authorizing the execution of Change Order No. Two (2) - Final for Parish Project No. P030704, East Bank Historical Lighting, to decrease the contract amount by $1,959.67 and to increase the contract time by 10 calendar days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: Highway Dept. (Decorative Lighting Along River Road - LA 48) (EB Historical Lighting)
Attachments: 1. 2005-0063 Change Order-F, 2. 2005-0063 Final Ord 05-3-7 with Change Order
Related files: 2004-0202, 2004-0118
2005-0063
INTRODUCED BY:      ALBERT D. LAQUE, PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.                   
Title
An ordinance approving and authorizing the execution of Change Order No. Two (2) - Final for Parish Project No. P030704, East Bank Historical Lighting, to decrease the contract amount by $1,959.67 and to increase the contract time by 10 calendar days.
Body
WHEREAS,      Ordinance No. 04-6-11 adopted June 8, 2004 by the St. Charles Parish Council approved and authorized the execution of Change Order One (1) for Parish Project No. P030704, East Bank Historical Lighting, to increase the contract by $25,481.44.
WHEREAS,      Ordinance No. 04-4-3 adopted April 5, 2004 by the St. Charles Parish Council approved and authorized the execution of a contract with All Star Electric for the installation of decorative lighting along River Road (LA 48) in the amount of $148,912.91.
WHEREAS,      it is necessary to decrease the original contract in the amount of $1,959.67 and to increase the contract time by 10 calendar days to balance actual quantities.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      To approve and authorize the execution of Change Order No. Two (2) - Final for Parish Project No. P030704, East Bank Historical Lighting, to decrease the contract amount by $1,959.67 and to increase the contract time by 10 calendar days; and,
SECTION II.      That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this            day of                       , ______,to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:                                     
SECRETARY:                                     
DLVD/PARISH PRESIDENT:                         
APPROVED:                         DISAPPROVED:             
 
PARISH PRESIDENT:                               
RETD/SECRETARY:                               
AT:                              RECD BY: