logo  ST. CHARLES PARISH, LA
File #: 2022-0356    Version: 1 Name: C.O. No.1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. (P080905-5F, CPRA Project No. BA-0244)
Type: Ordinance Status: Enacted
File created: 1/9/2023 In control: Parish Council
On agenda: 1/23/2023 Final action: 1/23/2023
Enactment date: Enactment #: 23-1-5
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $113,705.00 and increase the contract time by ninety (90) days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: Grants, Hurricane Protection Levee (WB - Ellington), Hurricane Protection Levee (WB - Kellogg Pump Station T-Wall), Public Works (Dept. of)
Attachments: 1. 2022-0356 10475-0344_Kellogg CO #001_Package, 2. 2022-0356 Final Ord 23-1-5 with change order
Related files: 2022-0063, 2018-0324, 2013-0339, 2018-0226, 2018-0292, 2022-0195, 2017-0354, 2019-0163, 2020-0281, 2020-0324, 2021-0101, 2024-0137
2022-0356
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ______________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $113,705.00 and increase the contract time by ninety (90) days.
Body
WHEREAS, Ordinance No. 22-3-12, adopted March 21, 2022 by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc, for Ellington Structures - Kellogg Pump Station T-Wall, Project No. P080905-5F, CPRA Project No. BA-0244, in the amount of $4,323,888.00; and,
WHEREAS, Resolution No. 6522, adopted on November 16, 2020, approved an Intergovernmental Agreement with the State of Louisiana through the Coastal Protection and Restoration Authority Board to provide $2,500,000.00 in funding for construction costs for said project; and,
WHEREAS, Ordinance No. 08-10-7 adopted October 20, 2008 approved and authorized the execution of a Contract for Engineering Services with BURK-KLEINPETER, INC. for necessary professional engineering services associated with Parish Project No. P080905 St. Charles Parish West Bank Hurricane Protection Levee and Urban Flood Control; and,
WHEREAS, Change Order No. 1 is a result of changes within the scope of the contract to address Geotech conditions not previously identified and to adjust T-Wall design to fit field conditions within the Construction Contract resulting in the lengthening of 33 batter "H" piles; and,
WHEREAS, the increase in contract amount by $113,705.00 is a result of deletion of two (2) bid line items, the addition of two (2) new line items, and increase in quantity of one 91 (1) bid line item; and,
WHEREAS, the increase in contract time by ninety (90) days is due to delay caused by pile load test no...