An ordinance approving and authorizing the execution of Change Order No. 1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $113,705.00 and increase the contract time by ninety (90) days.
Body
WHEREAS, Ordinance No. 22-3-12, adopted March 21, 2022 by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc, for Ellington Structures - Kellogg Pump Station T-Wall, Project No. P080905-5F, CPRA Project No. BA-0244, in the amount of $4,323,888.00; and,
WHEREAS, Resolution No. 6522, adopted on November 16, 2020, approved an Intergovernmental Agreement with the State of Louisiana through the Coastal Protection and Restoration Authority Board to provide $2,500,000.00 in funding for construction costs for said project; and,
WHEREAS, Ordinance No. 08-10-7 adopted October 20, 2008 approved and authorized the execution of a Contract for Engineering Services with BURK-KLEINPETER, INC. for necessary professional engineering services associated with Parish Project No. P080905 St. Charles Parish West Bank Hurricane Protection Levee and Urban Flood Control; and,
WHEREAS, Change Order No. 1 is a result of changes within the scope of the contract to address Geotech conditions not previously identified and to adjust T-Wall design to fit field conditions within the Construction Contract resulting in the lengthening of 33 batter "H" piles; and,
WHEREAS, the increase in contract amount by $113,705.00 is a result of deletion of two (2) bid line items, the addition of two (2) new line items, and increase in quantity of one 91 (1) bid line item; and,
WHEREAS, the increase in contract time by ninety (90) days is due to delay caused by pile load test no...