File #: 2014-0013    Version: 1 Name: Change Order No. 1 (Final) for Project No. P130103, Storm Window Retrofit Public Works Office Building Project
Type: Ordinance Status: Enacted
File created: 1/21/2014 In control: Parish Council
On agenda: Final action: 2/3/2014
Enactment date: 2/3/2014 Enactment #: 14-2-3
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Project No. P130103, Storm Window Retrofit Public Works Office Building Project to decrease the contract amount by $15,000.00 and decrease the contract time by thirty two (32) days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: Public Works (Dept. of) (Storm Window Retrofit Proj.)
Attachments: 1. 2014-0013 CO No 1 Final for Storm Window Project P130103, 2. 2014-0013 Change Order-F, 3. 2014-0013 Final Ord 14-2-3 with Change Order
Related files: 2013-0104, 2013-0324
2014-0013
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Project No. P130103, Storm Window Retrofit Public Works Office Building Project to decrease the contract amount by $15,000.00 and decrease the contract time by thirty two (32) days.
body
WHEREAS, Ordinance No. 13-9-12, adopted September 16, 2013, by the St. Charles Parish Council, approved and authorized the execution of a contract with Wainwright Construction, Inc. Project No. P130103, Storm Window Retrofit Public Works Office Building Project in the amount of $124,432.00; and,
WHEREAS, The decrease in the lump sum contract amount resulted from the decrease of one (1) Schedule of Values line item in the amount of $15,000.00; and,
WHEREAS, The decrease in contract time of thirty two (32) days was a result of a reduction in days due to completion of work in advance of the originally scheduled Completion Date.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. 1(Final) for Parish Project No. P130103, Storm Window Retrofit Public Works Office Building Project to decrease the contract amount by $15,000.00 and decrease the contract time by thirty two (32) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ____________, 2014
to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________