2003-0410
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.:
title
An ordinance approving and authorizing the execution of Change Order No. One (1) - Final for Parish Project No. P021201, Road Maintenance 2003, to decrease the contract amount by $2,265.60 and to decrease the contract time by 96 days.
Body
WHEREAS, Ordinance No. 03-9-16, adopted September 22, 2003, by the St. Charles Parish Council awarded construction of Parish Project No. P021201, Road Maintenance 2003, to Barriere Construction Co., L.L.C.; and,
WHEREAS, it is necessary to amend the contract to adjust the original contract quantities with actual quantities resulting in a decrease of $2,265.60 in the contract amount and a decrease in the contract time by 96 calendar days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. One (1) - Final for the Road Maintenance 2003 contract to decrease the contract amount by $2,265.60 and to decrease the contract time by 96 days is hereby approved.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing Ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2004, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: