logo  ST. CHARLES PARISH, LA
File #: 2021-0101    Version: 1 Name: Accept the work as complete for the Ellington Pump Station, State Project No. H.13148, through DOTD under the Louisiana Statewide Flood Control Program
Type: Resolution Status: In Council - Resolutions
File created: 4/19/2021 In control: Parish Council
On agenda: 4/19/2021 Final action: 4/19/2021
Enactment date: Enactment #: 6555
Title: A resolution requesting authorization for St. Charles Parish to accept the work as complete for the Ellington Pump Station, State Project No. H.13148, through the State of Louisiana Department of Transportation and Development (DOTD) under the Louisiana Statewide Flood Control Program.
Sponsors: Matthew Jewell, Department of Public Works, Grants Office
Indexes: Grants, Hurricane Protection Levee (WB - Ellington), Public Works (Dept. of)
Attachments: 1. 2021-0101 Final Reso 6555, 2. 2021-0101 Acceptance - F
Related files: 2013-0339, 2017-0354, 2018-0226, 2018-0292, 2018-0324, 2019-0163, 2020-0281, 2022-0356, 2022-0063

2021-0101

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS & GRANTS OFFICE)

RESOLUTION NO.                                            

Title

A resolution requesting authorization for St. Charles Parish to accept the work as complete for the Ellington Pump Station, State Project No. H.13148, through the State of Louisiana Department of Transportation and Development (DOTD) under the Louisiana Statewide Flood Control Program.

Body

WHEREAS,                     St. Charles Parish has successfully completed the Ellington Pump Station flood control project under the Statewide Flood Control Program by way of Certificate of Final Acceptance issued on October 6, 2020; and,

WHEREAS,                     the Louisiana Statewide Flood Control Program requires a resolution accepting the work.

NOW, THEREFORE, BE IT RESOLVED, THAT WE, THE MEMBERS OF THE ST. CHARLES PARISH COUNCIL, do hereby consider this project complete and accept all improvements and modifications installed during the execution of the Ellington Pump Station, State Project No. H.013148.

The foregoing resolution having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the resolution was declared adopted this             day of                      , 2021, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED :                       DISAPPROVED:                                           

 

PARISH PRESIDENT:                                                                                                          

RETD/SECRETARY:                                                                                                           

AT:                        RECD BY: