File #: 2016-0182    Version: 1 Name: Change Order No. 1 for the St. Charles Parish EOC Grounding Project
Type: Ordinance Status: Enacted
File created: 4/18/2016 In control: Parish Council
On agenda: 5/2/2016 Final action: 5/2/2016
Enactment date: Enactment #: 16-5-8
Title: An ordinance to approve and authorize the execution of Change Order No. 1 for the St. Charles Parish EOC Grounding, Parish Project No. P150701, to increase the contract time by thirty-eight (38) days at no cost to St. Charles Parish.
Sponsors: Lawrence 'Larry' Cochran, Department of Emergency Preparedness
Indexes: Em. Prep. (Dept. of) (Grounding)
Attachments: 1. 2016-0182 Change Order No. 1 - EOC Grounding, 2. 2016-0182 Change Order-F, 3. 2016-0182 Final Ord 16-5-8 with Change Order
Related files: 2009-0363, 2009-0442, 2010-0098, 2010-0299, 2011-0309, 2011-0374, 2012-0394, 2013-0085, 2013-0198, 2013-0481, 2015-0050, 2015-0316, 2019-0296, 2019-0269, 2016-0275

2016-0182

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF EMERGENCY PREPAREDNESS)

ORDINANCE NO.                                                                

Title

An ordinance to approve and authorize the execution of Change Order No. 1 for the St. Charles Parish EOC Grounding, Parish Project No. P150701, to increase the contract time by thirty-eight (38) days at no cost to St. Charles Parish.

Body

WHEREAS,                     Ordinance No. 15-10-6 adopted October 5th, 2015, by the St. Charles Parish Council, approved and authorized the execution of a contract with Tasch Electric, LLC, for the construction of R56 standard electrical grounding and an uninterruptible power supply at the St. Charles Parish Emergency Operations Center at 15026 River Road in Hahnville, in the amount of $350,000; and,

WHEREAS,                     the increase in contract time of thirty-eight (38) days is related to a delay in the delivery of the UPS equipment; and,

WHEREAS,                     there will be no cost associated with the increase in contract time to St. Charles Parish.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That Change Order No. 1 for the St. Charles Parish EOC Grounding, Parish Project No. P150701, to increase the contract time by thirty-eight (38) days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this              day of                      , 2016, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED:                         DISAPPROVED:                                           

 

PARISH PRESIDENT:                                                                                                          

RETD/SECRETARY:                                                                                                          

AT:                              RECD BY: