2016-0182
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF EMERGENCY PREPAREDNESS)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of Change Order No. 1 for the St. Charles Parish EOC Grounding, Parish Project No. P150701, to increase the contract time by thirty-eight (38) days at no cost to St. Charles Parish.
Body
WHEREAS, Ordinance No. 15-10-6 adopted October 5th, 2015, by the St. Charles Parish Council, approved and authorized the execution of a contract with Tasch Electric, LLC, for the construction of R56 standard electrical grounding and an uninterruptible power supply at the St. Charles Parish Emergency Operations Center at 15026 River Road in Hahnville, in the amount of $350,000; and,
WHEREAS, the increase in contract time of thirty-eight (38) days is related to a delay in the delivery of the UPS equipment; and,
WHEREAS, there will be no cost associated with the increase in contract time to St. Charles Parish.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for the St. Charles Parish EOC Grounding, Parish Project No. P150701, to increase the contract time by thirty-eight (38) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2016, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: