An ordinance to approve and authorize the execution of a contract with W.L. Wyman Construction, Inc. for the Installation of the East Bank and West Bank Water Plant Shutters - HMGP #1603-089-0005 FEMA Project #0110 in the amount of $178,000.00.
Body
WHEREAS, sealed bids were received by the Parish on July 1, 2010, for the Installation of the East Bank and West Bank Water Plant Shutters - HMGP #1603-089-0005 FEMA Project #0110; and,
WHEREAS, installation of this project will protect the facilities from wind and debris damage and insure safety of St. Charles Parish employees in case of a Hurricane or related event; and,
WHEREAS, this project will be funded with an approved FEMA Hazard Mitigation Grant in the amount of $150,899.00 to assist the Parish in project funding; and,
WHEREAS, St. Charles Parish and the Governor's Office of Homeland Security and Emergency Preparedness have reviewed the bid and recommend that the Contract be awarded to the low bidder, W.L. Wyman Construction, Inc. in the amount of $178,000.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of W.L. Wyman Construction, Inc. for the Installation of the East Bank and West Bank Water Plant Shutters - HMGP #1603-089-0005 FEMA Project #0110 be hereby approved and accepted in the amount of $178,000.00.
SECTION II. That the Parish President is hereby authorized to execute said contract documents on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2010, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APP...
Click here for full text