logo  ST. CHARLES PARISH, LA
File #: 2014-0417    Version: 1 Name: Engineering Services Contract with Environmental Engineering Services, Inc. for the design of Parish Project No. S141201, Ellington Force Main Relocation
Type: Ordinance Status: Enacted
File created: 12/15/2014 In control: Parish Council
On agenda: 1/12/2015 Final action: 1/12/2015
Enactment date: Enactment #: 15-1-2
Title: An ordinance to approve and authorize the execution of an Engineering Services Contract with Environmental Engineering Services, Inc. for the design of Parish Project No. S141201, Ellington Force Main Relocation.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: Hurricane Protection Levee (WB - Ellington Levee Force Main Relocation), Public Works (Dept. of)
Attachments: 1. 2014-0417 Contract for Engineering Services signed by Engineer, 2. 2014-0417 Contract-F, 3. 2014-0417 Final Ord 15-1-2 with Contract
Related files: 2016-0392, 2017-0306
2014-0417
INTRODUCED BY: V.J. ST PIERRE, JR., PARISH PRESIDENT
(DERPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. __________
title
An ordinance to approve and authorize the execution of an Engineering Services Contract with Environmental Engineering Services, Inc. for the design of Parish Project No. S141201, Ellington Force Main Relocation.
body
WHEREAS, St. Charles Parish has plans to construction the West Bank Hurricane Protection Levee, Ellington Section; and,
WHEREAS, A twelve inch (12") wastewater force main is located within the construction area of the levee and would be damage beyond repair during levee construction; and,
WHEREAS, St. Charles Parish requires Parish Project No. S141201, Ellington Force Main Relocation be constructed before construction of the West Bank Hurricane Protection Levee, Ellington Section, can begin; and,
WHEREAS, This project requires professional services for the design and construction administration for the relocation of the force main; and,
WHEREAS, it is important that St. Charles Parish proceed with this project in order to protect the property and well-being of its citizens.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Engineering Services Contract with Environmental Engineering Services, Inc. for the design of Parish Project No. S141201, Ellington Force Main Relocation is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Engineering Services Contract on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ___________, 2015, to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DIS...

Click here for full text