2025-0395
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of a Contract with Hard Rock Construction, LLC, for the Kinler Lift Station Replacement (Project No. S220801), in the amount of $624,712.60.
Body
WHEREAS, Ordinance No. 22-10-6 adopted on October 17, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Fairway Consulting and Engineering, LLC, to perform engineering services for the Kinler Lift Station Replacement (Project No. S220801), in the not to exceed amount of $208,859.00; and,
WHEREAS, sealed bids were received by St. Charles Parish on December 2, 2025, for the Kinler Lift Station Replacement (Project No. S220801); and,
WHEREAS, Fairway Consulting and Engineering, LLC has reviewed the bids and recommends that the Contract be awarded to the lowest responsive and responsible bidder, Hard Rock Construction, LLC, in the amount of $624,712.60.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Hard Rock Construction, LLC, for the construction of Kinler Lift Station Replacement (Project No. S220801), is hereby approved and accepted in the amount of $624,712.60.
SECTION II. That the Parish President is hereby authorized to execute said Contract on behalf of St. Charles Parish.
SECTION III. A final Notice of Contract shall be printed and filed in place of the contract documents with the St. Charles Parish Clerk of Court and in the records of the St. Charles Parish Council.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2026, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED : ...
Click here for full text