logo  ST. CHARLES PARISH, LA
File #: 2024-0229    Version: 1 Name: C.O. 1 - Final for the East Bank ā€œCā€ Plant Filter Upgrade (Project No. WWKS-96) to decrease the contract amount by $7,848.00 and increase the contract time by one hundred five (105) days
Type: Ordinance Status: Public Hearing
File created: 6/17/2024 In control: Parish Council
On agenda: 7/8/2024 Final action:
Enactment date: Enactment #:
Title: An ordinance approving and authorizing the execution of Change Order No. 1 - Final for the East Bank "C" Plant Filter Upgrade (Project No. WWKS-96) to decrease the contract amount by $7,848.00 and increase the contract time by one hundred five (105) days.
Sponsors: Matthew Jewell, Department of Waterworks
Attachments: 1. 2024-0229 East Bank C Plant Upgrade - WWKS 96 Change Order
Related files: 2021-0198, 2021-0117, 2018-0147, 2023-0052
2024-0229
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO. __________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 - Final for the East Bank "C" Plant Filter Upgrade (Project No. WWKS-96) to decrease the contract amount by $7,848.00 and increase the contract time by one hundred five (105) days.
Body
WHEREAS, Ordinance No. 18-6-5 adopted on June 4, 2018, by the St. Charles Parish Council, approved and authorized the execution of a contract for Engineering Services between GSA Consulting Engineers and St. Charles Parish for necessary professional engineering services associated with the East Bank C Plant Filter Upgrade (WWKS 96); and,
WHEREAS, Ordinance No. 21-5-5 adopted on May 3, 2021, by the St. Charles Parish Council, approved and authorized Amendment No. 1 to Ordinance No. 18-6-5 which approved a contract for Engineering Services with GSA Consulting Engineers for necessary professional engineering services associated with Parish Project No. WWKS 96, East Bank C Plant Filter Upgrade; and,
WHEREAS, Resolution No. 6572 adopted on July 26, 2021, by the St. Charles Parish Council, approved and authorized the execution of a letter by St. Charles Parish approving McKim & Creed, Inc. as assignee in title of GSA Consulting Engineers in connection with the Engineering Services Contract with GSA Consulting Engineers, for the East Bank C Plant Filter Upgrade (WWKS 96); and,
WHEREAS, Ordinance No. 23-3-4 adopted March 27, 2023, by the St. Charles Parish Council, approved and authorized the execution a contract with Pintail Contracting Services, LLC, for the East Bank "C" Plant Filter Upgrade (Project No. WWKS-96) in the amount of $2,023,900.00; and,
WHEREAS, it is necessary to decrease the construction contract amount by $7,848.00 due to a decrease of $2,353.00 for miscellaneous concrete repairs, and a decrease of $5,495.00 for stainless steel angle supports for surface sweeps;...

Click here for full text