2016-0118
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. __________
Title
An ordinance to approve and authorize the execution of Change Order No. 2 for Parish Project No. P130101, Cousins Pump Station Discharge Pipe Replacement.
Body
WHEREAS, Ordinance No. 15-7-7 adopted July 6, 2015 by the St. Charles Parish Council awarded construction of Parish Project No P130101, Cousins Pump Station Discharge Pipe Replacement, to Kostmayer Construction, LLC; and,
WHEREAS, Ordinance No. 15-12-7 adopted December 14, 2015 by the St. Charles Parish Council authorizing the execution of Change Order 1 to increase the contract amount by $54,000 and increase the contract time by forty (40) days; and,
WHEREAS, it is necessary to amend the contract to adjust the original contract quantities with final quantities resulting in an increase to the contract amount by $358.75 and an increase in time of twenty-two (22) days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 2 for Parish Project No. P130101, Cousins Pump Station Discharge Pipe Replacement, to increase the contract amount by $358.75 and increase the time by twenty-two (22) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2016,
to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:______________...