logo  ST. CHARLES PARISH, LA
File #: 2015-0467    Version: 1 Name: Contract with Fleming Construction Company, LLC for Parish Project No. P130601, Sunset Pump Station Improvements, in the amount of $862,735.00 which is the Base Bid
Type: Ordinance Status: Enacted
File created: 12/14/2015 In control: Parish Council
On agenda: 1/12/2016 Final action: 1/12/2016
Enactment date: Enactment #: 16-1-4 AMENDED
Title: An ordinance to approve and authorize the execution of a Construction Contract with Fleming Construction Company, LLC for Parish Project No. P130601, Sunset Pump Station Improvements, in the amount of $862,735.00 which is the Base Bid.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: Public Works (Dept. of), Sunset Drg. District Pump Station Imp.
Attachments: 1. 2015-0467 Introduction of Ordinance for Sunset PS P130601, 2. 2015-0467 BW Extra Info, 3. 2015-0467 Contract-F, 4. 2015-0467 Final Ord 16-1-4 with Contract, 5. 2015-0467 Notice of Contract-F, 6. 2015-0467 Completion-F, 7. 2015-0467 Acceptance-F
Related files: 2014-0332, 2014-0320, 2013-0249, 2013-0231, 2015-0160, 2017-0217
2015-0467
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance to approve and authorize the execution of a Construction Contract with Fleming Construction Company, LLC for Parish Project No. P130601, Sunset Pump Station Improvements, in the amount of $862,735.00 which is the Base Bid.
Body
WHEREAS, sealed bids were received by St Charles Parish November 16, 2015 for Project No. P130601, Sunset Pump Station Improvements, and;
WHEREAS, Evans-Graves Engineers Inc., the Engineer for the Project, has reviewed the bids and recommended that the contract be awarded to the low bidder, Fleming Construction Company, LLC in the amount of $862,735.00 which is the Base Bid; and,
WHEREAS, installation of this project generally comprises furnishing and installing two (2)-30" fresh water hydraulic pumps, drive units, and fuel tank on platforms in the intake of the Sunset Drainage Pumping Station, with associated piping. The Contract Work will be located generally in Bayou Gauche on the West Bank of St. Charles Parish, at the Sunset Pump Station located at coordinates 290 47' 18.88" N and 900 25" 45.72" W.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Fleming Construction Company, LLC for the construction of St. Charles Parish Project No. P130601, Sunset Pump Station Improvements, is hereby approved and accepted, in the amount of $862,735.00.
SECTION II. That the Parish President is hereby authorized to execute said contract documents on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ____________, 2016, to become effective five (5) days after publication in the Official Journal.