logo  ST. CHARLES PARISH, LA
File #: 2013-0131    Version: Name: Change Order No. 1 for Parish Project No. P091001, Drainage Improvements to KCS Canal Project to increase the contract amount by $64,861.20 and increase the contract time by eighty three (83) days
Type: Ordinance Status: Enacted
File created: 4/8/2013 In control: Parish Council
On agenda: Final action: 4/22/2013
Enactment date: 4/22/2013 Enactment #: 13-4-11
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. P091001, Drainage Improvements to KCS Canal Project to increase the contract amount by $64,861.20 and increase the contract time by eighty three (83) days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Montz Drg. - KCS Canal Imp.)
Attachments: 1. Construction Change Directive No 2.PDF, 2. Construction Change Directive No. 1.pdf, 3. Ordinance and Change Order.PDF, 4. 2013-0131 Change Order-F, 5. 2013-0131 Final Ord 13-4-11 with Change Order
Related files: 2013-0297, 2012-0199, 2010-0044, 2023-0156
2013-0131
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. P091001, Drainage Improvements to KCS Canal Project to increase the contract amount by $64,861.20 and increase the contract time by eighty three (83) days.
Body
WHEREAS, Ordinance No. 12-6-7, adopted June 4, 2012, by the St. Charles Parish Council, approved and authorized the execution of a contract with Hamp's Construction, LLC for Parish Project No. P091001, Drainage Improvements to KCS Canal Project in the amount of $1,199,737.81; and,
WHEREAS, The increase in contract amount resulted from two (2) Construction Change Directives due to a work stoppage implemented for site remediation of asbestos, performed by the KCS Railroad. An increase of $16,656.38 was a result of Change Directive #1 for demobilization from the project site. An Increase of $46,864.82 was a result of Change Directive #2 for remobilization and to bring the condition of the project site back to the construction status prior to demobilization. Two (2) additional line items are added and one (1) line item increased which represents all cost associated with the work stoppage due to remediation of asbestos at the project site by the KCS Railroad; and,
WHEREAS, The increase in contract time was a result of days incurred from work stoppage due to the site remediation of asbestos by the KCS Railroad.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. 1 for Parish Project No. P091001, Drainage Improvements to KCS Canal Project to increase the contract amount by $64,861.20 and increase the contract time by eighty three (83) days.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.