File #: 2003-0042    Version: 1 Name: C.O. 3 - Final for Parish Project No. P980703 Destrehan I Pump Station to balance contractual quantities with actual quantities
Type: Ordinance Status: Enacted
File created: 2/3/2003 In control: Parish Council
On agenda: Final action: 2/17/2003
Enactment date: 2/17/2003 Enactment #: 03-2-19
Title: An ordinance approving and authorizing the execution of Change Order No. Three (3) - Final for Parish Project No. P980703 Destrehan I Pump Station to balance contractual quantities with actual quantities.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Destrehan I Pump Station Upgrade)
Attachments: 1. 2003-0042 Change Order-F, 2. 2003-0042 Final Ord 03-2-19 with Change Order
Related files: 2002-0060, 2002-0065, 2001-0387, 2002-0005, 2002-0394
2003-0042
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. Three (3) - Final for Parish Project No. P980703 Destrehan I Pump Station to balance contractual quantities with actual quantities.
Body
WHEREAS, Ordinance No. 01-11-4 adopted November 5, 2001 by the St. Charles Parish Council, approved and authorized the execution of a contract with Boh Bros. Construction Company, L.L.C. for the construction of Destrehan I Pump Station Upgrade in the amount of $3,179,684.00; and,
WHEREAS, Ordinance No. 02-2-2 adopted February 18, 2002 by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to the Engineering Services Contract with URS Corporation to provide the necessary services in moving all construction outside of railroad right-of-way due to the lack of issuance of a railroad permit; and,
WHEREAS, Ordinance No. 02-2-4 adopted February 18, 2002 by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 to the contract, which changed various bid form items to lump sum and corrected the contract time to 300 days; and,
WHEREAS, Ordinance No. 02-10-1 adopted October 7, 2002 by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 2 to the contract, which moved all construction outside of the railroad right-of-way; and,
WHEREAS, Change Order No. Three (3) - Final is necessary to close out the contract with Boh Bros. Construction Company, L.L.C. for the construction of Parish Project No. P980703, Destrehan I Pump Station Upgrade.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. Three (3) to the contract for Parish Project No. 980703, Destrehan I Pump Station Upgrade, to reduce contract time by six (6) days and contract amount by four thousand eight hundred ninety-two dollars and 28 cents ($489...