2010-0384
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. P080802-1, Montz Drainage Plan Implementation - Thoroughbred Ave Culvert Replacement Project to decrease the contract amount by $70,361.00 and increase the contract time by fifty three (53) days.
Body
WHEREAS, Ordinance No. 10-5-7, adopted May 3, 2010, by the St. Charles Parish Council, approved and authorized the execution of a contract with LA Contracting Enterprise, LLC for Parish Project No. P0080802-1 Montz Drainage Plan Implementation - Thoroughbred Ave Culvert Replacement Project in the amount of $259,865.00; and,
WHEREAS, The decrease in contract amount resulted from the deletion of two line items in the amount of $79,650, decreasing three line items in the amount of $7,553, and increasing three line items in the amount of $16,842; and,
WHEREAS, The increase in contract time was a result of rain days incurred, schedule delays due to SCP Utility requirements not anticipated in the engineering estimate of construction time and minor scope change due to subsurface conflicts.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1(Final) for Parish Project No. P080802-1, Montz Drainage Plan Implementation - Thoroughbred Ave Culvert Replacement Project to decrease the contract amount by $70,361.00 and increase the contract time by fifty three (53) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _____ day of ____________, 2010, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:__________________...
Click here for full text