An ordinance to approve and authorize the execution of a contract with HHP Construction Group, LLC for the construction of the Norco 5th Street Sidewalk Project, State Project No. H.006592, Control Section No. 000-45, Federal Aid Project No. 4509(501) with Bid in the amount of $230,287.00.
Body
WHEREAS, The Louisiana Department of Transportation and Development (LADOTD) opened bids on August 8, 2012 for the above referenced project; and,
WHEREAS, LaDOTD and St. Charles Parish have reviewed said bids and recommend that the project be awarded to the low bidder, HHP Construction Group LLC, in the amount of $230,287.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of HHP Construction Group, LLC for the construction of the Norco 5th Street Sidewalk Project, State Project No. H.006592, Control Section No. 000-45, Federal Aid Project No. 4509(501), is hereby accepted and approved, in the amount of $230,287.00.
SECTION II. That the Parish President is hereby authorized to execute said contract documents on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2012,
to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________RECD BY: _____________________________