File #: 2015-0390    Version: 1 Name: Change Order No. 3 (Final) for West Bank Multi-Use Path Phase III, to correct dollar amounts
Type: Ordinance Status: Enacted
File created: 10/19/2015 In control: Parish Council
On agenda: 11/2/2015 Final action: 11/2/2015
Enactment date: Enactment #: 15-11-14
Title: An ordinance approving and authorizing the execution of Change Order No. 3 (Final) for Parish Project No. P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500) to correct dollar amounts in the amount of $202.05.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: P and R (Dept. of) (WB Bike Path), Public Works (Dept. of)
Attachments: 1. 2015-0390 C.O. No. 3 - WB Multi-Use Path, Ph. III, 2. 2015-0390 Change Order-F, 3. 2015-0390 Final Ord 15-11-14 with Change Order
Related files: 2015-0012, 2014-0334, 2011-0166, 2012-0093, 2012-0128, 2013-0373, 1999-5027, 2002-0069, 2003-0253, 2005-0193, 2009-0145, 2002-0342, 2003-0060, 2005-0202, 2004-0276, 2006-0153, 2006-0238, 2007-0316, 2009-0487, 2010-0132, 2003-0397, 2009-0106, 2009-0198, 2009-0307, 2009-0364, 2009-0467, 2010-0154, 2010-0370, 2011-0023, 2015-0013, 2009-0278, 2017-0409, 2016-0417, 2018-0145, 2018-0183, 2020-0347
2015-0390
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ____________
Title
An ordinance approving and authorizing the execution of Change Order No. 3 (Final) for Parish Project No. P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500) to correct dollar amounts in the amount of $202.05.
Body
WHEREAS, Ordinance No. 12-3-1 adopted March 12, 2012, by the St. Charles Parish Council awarded construction of Parish Project No. P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500), to Barriere Construction Co., LLC; and,
WHEREAS, Ordinance No. 13-10-16 adopted October 21, 2013, by the St. Charles Parish Council increased the contract amount by $151,603.68 and increased the contract time by thirty (30) days; and,
WHEREAS, Ordinance No. 14-10-16 adopted October 24, 2014, by the St. Charles Parish Council increased the contract amount by $2,454.54; and,
WHEREAS, the Louisiana Department of Transportation and Development Construction Audit section discovered that an incorrect percentage of asphalt was used in calculations related to the Asphalt Price Adjustment; thereby to correct the line item an increase of $202.05 is required to the contract.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 3 (Final) for Parish Project No. P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500) to increase the contract amount by $202.05 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
SECTION III. St. Charles Parish considers the project complete and accepts all improvements and modifications installed during execution of the project.
The foregoing ordinance having been submitted to a vote, the vote thereon...