logo  ST. CHARLES PARISH, LA
File #: 2023-0157    Version: 1 Name: Amendment No. 2 to Ord. No. 19-7-3 which approved the Prof. Serv. Agree. with Picciola & Associates, Inc., to perform engineering services for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101)
Type: Ordinance Status: Enacted
File created: 6/19/2023 In control: Parish Council
On agenda: 7/10/2023 Final action: 7/10/2023
Enactment date: Enactment #: 23-7-5
Title: An ordinance approving and authorizing the execution of an Amendment No. 2 to Ordinance No. 19-7-3 which approved the Professional Services Agreement with Picciola & Associates, Inc., to perform engineering services for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the not to exceed amount of $111,500.00.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Canal Imp. Near Destrehan Pump Station No. 2), Public Works (Dept. of)
Attachments: 1. 2023-0157 P181101 - Legal Amendment Template, 2. 2023-0157 Exhibit A, 3. 2023-0157 PAI Corporate Resolution SCP, 4. 2023-0157 Final Ord 23-7-5 with amendment
Related files: 2020-0200, 2023-0099, 2019-0193, 2023-0143, 2023-0141, 2024-0119
2023-0157
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of an Amendment No. 2 to Ordinance No. 19-7-3 which approved the Professional Services Agreement with Picciola & Associates, Inc., to perform engineering services for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the not to exceed amount of $111,500.00.
Body
WHEREAS, a Professional Services Agreement was fully executed November 1, 2018, between St. Charles Parish and Picciola & Associates, Inc., to complete a conceptual study for Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101) in the not to exceed amount of $15,918.00; and,
WHEREAS, Ordinance No. 19-7-3 adopted July 1, 2019, by the St. Charles Parish Council approved and authorized the execution of a professional service multi-phase project agreement with Picciola & Associates, Inc. to perform professional design services for Destrehan Pump Station (P.S.) No. 2 (Conveyance Improvements) (P181101), in the amount not to exceed $183,375.00; and,
WHEREAS, Ordinance No. 20-7-13 adopted July 27, 2020, by the St. Charles Parish Council approved and authorized the execution of Amendment No.1 to the professional services agreement with Picciola & Associates, Inc., to include additional design work due to scope changes for Destrehan Pump Station (P.S.) No. 2 (Conveyance Improvements) (P181101), in the amount not to exceed $54,927.00, increasing the total not to exceed design fee to $238,302.00; and,
WHEREAS, on June 19, 2023, St. Charles Parish Council will consider File No. 2023-0141 to approve and authorize the execution of a contract with Sealevel Construction, Inc., for Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the amount of $9,190,697.00; and,
WHEREAS, on June 19, 2023, St. Charles Parish Council will consider File No. 2023-0143 to ...