File #: 2014-0084    Version: 1 Name: Change Order No. 1 for Willowridge Levee - Phase I, as part of the West Bank Hurricane Protection Levee Project
Type: Ordinance Status: Enacted
File created: 3/24/2014 In control: Parish Council
On agenda: 4/7/2014 Final action: 4/7/2014
Enactment date: Enactment #: 14-4-1
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Project No. P080905-3B, Willowridge Levee - Phase I, State Project No.H.009257, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $214,600.00 and increase the contract time by ninety (90) days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: Floods, Hurricane Protection Levee (WB - Willowridge Levee Imp., Ph. I)
Attachments: 1. 2014-0084 Change Order 1 Willowridge Levee Ph I, 2. 2014-0084 Change Order-Final, 3. 2014-0084 Final Ord 14-4-1 with Change Order
Related files: 2017-0227, 2015-0340, 2011-0257, 2013-0407, 2008-0418, 2013-0411, 1999-5052, 2000-0144, 2013-0408, 2011-0057, 2011-0058, 2011-0088, 2011-0233, 2012-0081, 2012-0294, 2013-0262, 2014-0279, 2015-0104, 2015-0105, 2015-0106, 2015-0108, 2015-0109, 2015-0116, 2015-0146, 2015-0205, 2015-0308, 2015-0309, 2015-0315
2014-0084
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ____________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Project No. P080905-3B, Willowridge Levee - Phase I, State Project No.H.009257, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $214,600.00 and increase the contract time by ninety (90) days.
Body
WHEREAS, Ordinance No. 13-11-6, adopted November 18, 2013, by the St. Charles Parish Council, approved and authorized the execution of a contract with Southern Delta Construction, LLC for Project No. P080905-3B, Willowridge Levee - Phase I, State Project No.H.009257, in the amount of $5,785,551.00; and,
WHEREAS, Change Order No. 1 is a result of a change within the scope of the contract to increase the elevation of the levee from +5.5' elevation to +7.5' elevation; and,
WHEREAS, current construction activities have revealed that there is less unsuitable organic material on the construction site than previously anticipated, resulting in additional suitable levee embankment material available for levee construction at the levee location. This additional material must be hauled to the staging area and handled again at a later date, if the +7.5' levee elevation is not constructed at this time; and,
WHEREAS, the increase in contract amount of $214,600.00 is a result of the increase in five (5) bid line items; and,
WHEREAS, the increase in contract time by ninety (90) days is a result of additional days projected to construct the Willowridge Levee to +7.5' elevation.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. 1 for Project No. P080905-3B, Willowridge Levee - Phase I, State Project No.H.009257, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $214,600.00 and increase the contract time by ninety (90) days is hereby approved an...