File #: 2025-0007    Version: 1 Name: C.O. No. 1 (Final) for the St. Charles Parish 1st Floor Courthouse Renovation (Project No. NO-GBCH023), to decrease the contract amount by $42,706.00 and increase the contract time by 11 days
Type: Ordinance Status: Enacted
File created: 1/27/2025 In control: Parish Council
On agenda: 2/10/2025 Final action: 2/10/2025
Enactment date: Enactment #: 25-2-2
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles Parish 1st Floor Courthouse Renovation (Project No. NO-GBCH023), to decrease the contract amount by $42,706.00 and increase the contract time by 11 days.
Sponsors: Matthew Jewell, General Government Buildings
Attachments: 1. 2024-0007 Change Order, 2. 2025-0007 Final Ord 25-2-2 with change order, 3. 2025-0007 Recordation Documents, 4. 2025-0007 Correspondence-Clerk 02.21.2025, 5. 2025-0007 Recordation Documents - Additional 6 Pages, 6. 2025-0007 Correspondence 02.24.2025, 7. 2025-0007 Recordation Documents - Clerk Correction
Related files: 2023-0219, 2024-0159
2025-0007
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(GENERAL GOVERNMENT BUILDINGS)
ORDINANCE NO. ____________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles Parish 1st Floor Courthouse Renovation (Project No. NO-GBCH023), to decrease the contract amount by $42,706.00 and increase the contract time by 11 days.
Body
WHEREAS, Ordinance No. 23-8-10 adopted on August 28, 2023, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Murray Architects Inc., to perform architectural, conceptual design, and construction management, etc. for the St. Charles Parish Courthouse 1st Floor Renovation (Project No. GBCH023), for a period of 12 months, in the not to exceed amount of $217,685.00; and,
WHEREAS, Ordinance No. 24-5-8 adopted on May 6 2024, by the St. Charles Parish Council, approved and authorized the execution of a Contract with Battco Construction and Maintenance, Inc., for the St. Charles Parish 1st Floor Courthouse Renovation (Project No. NO-GBCH023), in the amount of $1,965,000.00; and,
WHEREAS, St. Charles Parish and Battco Construction and Maintenance, Inc. have mutually agreed to decrease the contract amount by $42,706.00 and increase the contract time by 11 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (Final) for the St. Charles Parish 1st Floor Courthouse Renovation (Project No. NO-GBCH023), to decrease the contract amount by $42,706.00 and increase the contract time by 11 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ____________, 2025, to become effective five (5) days after publication in ...