2025-0268
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of a Contract with Anders Construction, Inc. for the Raw Water Intake Structure Access Bridge Pile Replacement (Project No. WWKS 112), in the amount of $201,670.00.
Body
WHEREAS, Ordinance No. 22-8-2 adopted on August 15, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Providence Engineering and Environmental Group, LLC, to perform engineering services for the Raw Water Intake Structure Pile Bent Replacement Project (Project No. WWKS 112), in the not to exceed amount of $86,800.00; and,
WHEREAS, sealed bids were received by the Parish on August 1, 2025, for the Raw Water Intake Structure Access Bridge Pile Replacement (Project No. WWKS 112); and,
WHEREAS, Providence Engineering has reviewed the bids and recommend that the Contract be awarded to the lowest responsible and responsive bidder, Anders Construction, Inc. in the amount of $201,670.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Anders Construction, Inc. for the Raw Water Intake Structure Access Bridge Pile Replacement (Project No. WWKS 112), in the amount of $201,670.00 be hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute the said Contract on behalf of St. Charles Parish.
SECTION III. A final Notice of Contract shall be printed and filed in place of the contract documents with the St. Charles Parish Clerk of Court and in the records of the St. Charles Parish Council.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2025, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY: