logo  ST. CHARLES PARISH, LA
File #: 2022-0273    Version: 1 Name: Professional Services Agreement w/Professional Engineering Consultants Corporation - Phase 3 Water Line Replacement in Bonnet Carre Spillway (Project No. WWKS 105)
Type: Ordinance Status: Enacted
File created: 9/19/2022 In control: Parish Council
On agenda: 10/3/2022 Final action: 10/3/2022
Enactment date: Enactment #: 22-10-1
Title: An ordinance approving and authorizing the execution of a Professional Services Agreement with Professional Engineering Consultants Corporation to perform engineering services for Phase 3 Water Line Replacement in Bonnet Carre Spillway (Project No. WWKS 105), in the not to exceed amount of $86,780.00.
Sponsors: Matthew Jewell, Department of Waterworks
Indexes: WW (Ph. 3 Water Main Replacement in Bonnet Carre Spillway)
Attachments: 1. 2022-0273 Agreement, Attachments, Exhibits, 2. 2022-0273 Corporate Resolution - SCPG, 3. 2022-0273 Certificate of Insurance - SCPG, 4. 2022-0273 Final Ord 22-10-1 with agreement
Related files: 2025-0058
2022-0273
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of a Professional Services Agreement with Professional Engineering Consultants Corporation to perform engineering services for Phase 3 Water Line Replacement in Bonnet Carre Spillway (Project No. WWKS 105), in the not to exceed amount of $86,780.00.
Body
WHEREAS, St. Charles Parish desires to replace 3,800 linear feet of HDPE water line; and,
WHEREAS, the projected work includes, but not limited to designing an eight (8) inch directionally drilled HDPE water line for approximately 3,800 linear feet with all appurtenances including all necessary permitting geotechnical testing and an estimated two (2) months of inspection; and,
WHEREAS, St. Charles Parish wishes to contract with Professional Engineering Consultants Corporation, to perform the Plan Development, Bidding and Advertising, and Construction for the Phase 3 Water Line Replacement in Bonnet Carre Spillway (Project No. WWKS 105) as described in Attachments A, B, and C.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Professional Services Agreement between St. Charles Parish and Professional Engineering Consultants Corporation to perform engineering services for Phase 3 Water Line Replacement in Bonnet Carre Spillway (Project No. WWKS 105), in the not to exceed amount of $86,780.00 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said agreement on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ____________, 2022, to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:

PARISH PRESIDENT:...

Click here for full text