2026-0252
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF ENGINEERING)
ORDINANCE NO. ___________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for the Destrehan Wastewater Treatment Plant Aeration Basin Rehabilitation (Project No. S211202), to increase the contract amount by $71,532.00 and increase the contract time by one hundred thirty-three (133) calendar days.
Body
WHEREAS, Ordinance No. 22-1-5 adopted on January 24, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Meyer Engineers, Ltd. for Destrehan Wastewater Treatment Plant Aeration Basin Rehabilitation (Project No. S211202), not to exceed $30,000.00; and,
WHEREAS, Ordinance No. 23-3-3 adopted on March 13, 2023, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to Ordinance No. 22-1-5 which approved the Professional Services Agreement with Meyer Engineers, Ltd., to perform engineering services for the Destrehan Wastewater Treatment Plant Aeration Basin Rehabilitation (Project No. S211202), increasing the overall not to exceed fee by $410,000.00, for a total contract value of $440,000.00; and,
WHEREAS, Ordinance No. 24-7-18 adopted on July 22, 2024, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 2 to Ordinance No. 22-1-5, which approved the Professional Services Agreement with Meyer Engineers, Ltd., to perform engineering services for the Destrehan Wastewater Treatment Plant Aeration Basin Rehabilitation (Project No. S211202), in the not to exceed amount of $110,000.00, for a total contract value of $550,000.00; and,
WHEREAS, Ordinance No. 24-9-9 adopted on September 23, 2024, by the St. Charles Parish Council, approved and authorized the execution of a Contract with NCMC, LLC for the Destrehan Wastewater Treatment Plant Aeration Basin Rehabilitation (Project No. S211202), in the amou...
Click here for full text