File #: 2016-0392    Version: 1 Name: Contract with Sealevel Construction, Inc., for Parish Project No. S141201 Ellington Levee Force Main Relocation
Type: Ordinance Status: Enacted
File created: 11/14/2016 In control: Parish Council
On agenda: 11/28/2016 Final action: 11/28/2016
Enactment date: Enactment #: 16-11-12 AMENDED
Title: An ordinance to approve and authorize the execution of a contract with Sealevel Construction, Inc., for Parish Project No. S141201 Ellington Levee Force Main Relocation with a Base Bid in the amount of $930,455.00.
Sponsors: Lawrence 'Larry' Cochran, Department of Wastewater
Indexes: Hurricane Protection Levee (WB - Ellington Levee Force Main Relocation), Public Works (Dept. of)
Attachments: 1. 2016-0392 Contract Sealevel, 2. 2016-0392 Temp. Serv.-F, 3. 2016-0392 Contract-F, 4. 2016-0392 Final Ord 16-11-12 with Contract, 5. 2016-0392 Notice of Contract-F, 6. 2016-0392 Work Change Directive, 7. 2016-0392 Completion-F, 8. 2016-0392 Acceptance-F
Related files: 2014-0417, 2015-0187, 2015-0243, 2015-0413, 2015-0184, 2017-0306, 2014-0046, 2015-0127, 2015-0183, 2015-0185, 2015-0186, 2018-0014, 2018-0094, 2019-0230, 2020-0041, 2020-0142

2016-0392

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF WASTEWATER)

ORDINANCE NO. __________

Title

An ordinance to approve and authorize the execution of a contract with Sealevel Construction, Inc., for Parish Project No. S141201 Ellington Levee Force Main Relocation with a Base Bid in the amount of $930,455.00.

Body

WHEREAS,                     sealed bids were received by St. Charles Parish on October 20, 2016, for Parish Project No. S141201 Ellington Levee Force Main Relocation; and,

WHEREAS,                     Environmental Engineering Service, Inc., Consulting Engineers for the Project, have reviewed the bids and recommend that the Base Bid in the amount of $930,455.00 by Sealevel Construction, Inc. be accepted.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That the bid of Sealevel Construction, Inc., for the construction of St. Charles Parish Project No. S141201 Ellington Levee Force Main Relocation, be hereby approved and accepted, in the amount of $930,455.00.

                     SECTION II.                     That the Parish President is hereby authorized to execute said contract documents on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ______ day of __________, 2016, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:______________________________________________

SECRETARY:_____________________________________________

DLVD/PARISH PRESIDENT:_________________________________

APPROVED:______________ DISAPPROVED:__________________

 

PARISH PRESIDENT:______________________________________

RETD/SECRETARY:_______________________________________

AT:_______________RECD BY: _____________________________