2009-0331
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1(Final) for Parish Project No. S080501-2, Destrehan WWTP Rehabilitation Phase II Headworks to decrease the contract amount by $28,771.97.
Body
WHEREAS, Ordinance No. 09-4-5, adopted April 6, 2009, by the St. Charles Parish Council, approved and authorized the execution of a contract with Cycle Construction Company for Destrehan WWTP Rehabilitation Phase II Headworks in the amount of $268,950.00; and,
WHEREAS, the decrease in contract amount resulted from the deletion of several line items in the bid that offset the increase in cost to repair unforeseen concrete damage beyond two inches of depth and other improvements; and,
WHEREAS, It is necessary to finally amend the contract deleting five items, and adding six items resulting in a decrease in the contract of $28,771.97.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. To approve and authorize the execution of Change Order No. 1(Final) for Parish Project No. S080501-2, Destrehan WWTP Rehabilitation Phase II Headworks to decrease the contract amount by $28,771.97.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _________ day of ____________, 2009, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________ RECD BY: ____________...
Click here for full text