2008-0194
INTRODUCED BY: V.J. ST. PIERRE, JR. PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P060405, Road Maintenance 2007, to increase the contract time by 11 days and to decrease the contract amount by $61,069.75.
Body
WHEREAS, Ordinance No. 07-7-6 adopted July 23, 2007 by the St. Charles Parish Council awarded construction of Parish Project No. P060405, Road Maintenance 2007, to Barriere Construction Company, LLC; and,
WHEREAS, it is necessary to amend the contract to adjust the original contract quantities with actual quantities resulting in an increase to the contract time by 11 days and a decrease to the contract amount by $61,069.75.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. 1 (Final) for Parish Project No. P060405, Road Maintenance 2007, to increase the contract time by 11 days and to decrease the contract amount by $61,069.75.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2008, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: